The application for stay was dismissed because the procurement process for Tender No. NCG/OT/31/2023-2024 was no longer live or capable of completion in 2025 due to statutory and regulatory constraints under the Public Procurement and Asset Disposal Act, which require procurement to be conducted within the relevant...

Source-derived case information.

Citation
[2025] KECA 875 (KLR)
Parties
Appellant: Ole Kina Ledama; Respondent: Narok County Government
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal (Application) E921 of 2024
Procedural Posture
Civil Appeal / Application for Stay Pending Appeal
Outcome
application dismissed
Judges
FA Ochieng, WK Korir, JM Ngugi
Legal Topics
Public Procurement, Stay of Execution, Constitutional Threshold, Public Interest Litigation, Budgetary Compliance, Judicial Discretion
Source Language
en
Constitutional Law Administrative Law Civil Procedure Public Procurement Stay of Execution Constitutional Threshold Public Interest Litigation Budgetary Compliance +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2
Sign in to unlock

Parties

Ole Kina Ledama

Appellant

Narok County Government

Respondent

Procedural Posture

Civil Appeal / Application for Stay Pending Appeal

  1. 1 Whether the applicant has met the threshold for grant of stay of execution under Rule 5(2)(b) of the Court of Appeal Rules.
  2. 2 Whether the procurement process for Tender No. NCG/OT/31/2023-2024 remains live and capable of completion in 2025.
  3. 3 Whether awarding a tender designated for the 2023-2024 financial year in 2025 is legally permissible under the Public Procurement and Asset Disposal Act.

Ratio Decidendi

The application for stay was dismissed because the procurement process for Tender No. NCG/OT/31/2023-2024 was no longer live or capable of completion in 2025 due to statutory and regulatory constraints under the Public Procurement and Asset Disposal Act, which require procurement to be conducted within the relevant fiscal year. The court found that the threat of the respondent proceeding with the impugned procurement process was speculative and legally doubtful, undermining the nugatory aspect required for a stay. While the appeal raised arguable constitutional issues, the lapse of the tender's financial year rendered a stay order unnecessary and ineffective.

Court Disposition

application dismissed

Orders

  • The applicant's application dated 21st November 2024 is dismissed.