[2025] KEHC 9744 (KLR)

[2025] KEHC 9744 (KLR)

The court found that the contract's five-month period was to be calculated from the actual commencement of works, not the date of signing. The Plaintiff commenced work after the kick-off meeting and submission of designs, making the effective contract period extend beyond the Defendant's claimed expiry date. The...

Source-derived case information.

Citation
[2025] KEHC 9744 (KLR)
Parties
Plaintiff: Limelight Creations Limited; Defendant: Kenya Pipeline Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case E390 of 2020
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the Plaintiff in part; Defendant's counterclaim partially allowed.
Judges
DO Chepkwony
Legal Topics
Breach of Contract, Contractual Milestones, Specific Performance, Quantum Meruit
Source Language
en
Commercial and Corporate Breach of Contract Contractual Milestones Specific Performance Quantum Meruit

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Limelight Creations Limited

Plaintiff

Kenya Pipeline Company Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the contract between the parties had expired before the dispute arose.
  2. 2 Whether there was breach of the contract by either party.
  3. 3 Whether the Plaintiff is entitled to the reliefs sought in the Plaint.

Ratio Decidendi

The court found that the contract's five-month period was to be calculated from the actual commencement of works, not the date of signing. The Plaintiff commenced work after the kick-off meeting and submission of designs, making the effective contract period extend beyond the Defendant's claimed expiry date. The Defendant's eviction of the Plaintiff from the site and refusal to attend Factory Acceptance Testing constituted a breach while the contract was still in force. However, the Plaintiff failed to provide sufficient documentary proof of payment and delivery for certain milestones, particularly regarding procurement and importation of equipment. The court held that only substantiated...

Court Disposition

Judgment for the Plaintiff in part; Defendant's counterclaim partially allowed.

Orders

  • Judgment entered for the Plaintiff against the Defendant in the sum of Kshs.9,599,346.60 less Kshs.6,399,564.40 already paid.
  • The Plaintiff is directed to deliver to the Defendant all goods purchased in accordance with the Bill of Quantities within seven (7) days of this Judgment and raise an invoice thereof; the Defendant shall pay for delivered goods as per the Bill of Quantities within seven days of receipt.