[2024] KEHC 5505 (KLR)

[2024] KEHC 5505 (KLR)

The court found that there was a contract in place between the parties containing an arbitration clause, and that the dispute regarding the validity of the termination and the rights under the contract was properly referable to arbitration. The court held that its jurisdiction under Section 7(1) of the Arbitration...

Source-derived case information.

Citation
[2024] KEHC 5505 (KLR)
Parties
Plaintiff: Logitech & Jibril Group Limited; Defendant: Kenya Ports Authority
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Miscellaneous Cause E041 of 2023
Procedural Posture
Miscellaneous Cause / Ruling on Chamber Summons for Interim Injunction Pending Arbitration
Outcome
Application partly allowed; only prayer (c) for preservation of the desalination plant granted; all other prayers dismissed; costs in the arbitration.
Judges
DKN Magare
Legal Topics
Arbitration Agreements, Interim Measures of Protection, Public Procurement Contracts, Mandatory and Prohibitory Injunctions
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreements Interim Measures of Protection Public Procurement Contracts Mandatory and Prohibitory Injunctions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 19 Party arguments 2
Sign in to unlock

Parties

Logitech & Jibril Group Limited

Plaintiff

Kenya Ports Authority

Defendant

Procedural Posture

Miscellaneous Cause / Ruling on Chamber Summons for Interim Injunction Pending Arbitration

  1. 1 Whether the court has jurisdiction to grant interim measures of protection under Section 7(1) of the Arbitration Act where the existence of an arbitration agreement is disputed.
  2. 2 Whether the applicant has established a prima facie case for the grant of an injunction to preserve the subject matter pending arbitration.
  3. 3 Whether the orders sought amount to specific performance or mandatory injunctions not grantable at the interlocutory stage.

Ratio Decidendi

The court found that there was a contract in place between the parties containing an arbitration clause, and that the dispute regarding the validity of the termination and the rights under the contract was properly referable to arbitration. The court held that its jurisdiction under Section 7(1) of the Arbitration Act was limited to granting interim measures of protection to preserve the subject matter pending arbitration, but not to grant orders amounting to specific performance or to restrain the floating of tenders where no evidence of imminent tenders was provided. The court determined that dismantling or interfering with the desalination plant would irreversibly alter the status quo...

Court Disposition

Application partly allowed; only prayer (c) for preservation of the desalination plant granted; all other prayers dismissed; costs in the arbitration.

Orders

  • Prayers a, b, and d of the application dated 30th October 2023 are dismissed.
  • An injunction is granted restraining the defendant, its workers, agents, servants, or any other persons acting pursuant to its authority, from interfering with, dismantling, removing, or in any other manner tampering with the plaintiff’s desalination plant, machinery, and other fixtures installed at the G-Section of...