[2013] KEHC 1855 (KLR)

[2013] KEHC 1855 (KLR)

The court found that while the plaintiff's lease had expired in July 2012, and there was evidence of rent arrears, the defendants were not justified in blockading the plaintiff's office without a court order. The court rejected the plaintiff's objection to the 1st defendant's authority to swear the affidavit,...

Source-derived case information.

Citation
[2013] KEHC 1855 (KLR)
Parties
Plaintiff: Lucy N. Momanyi t/a L. N. Momanyi & Company Advocates; Defendant: Joel Ombati Nyamweya; Defendant: Kenya Power & Lighting Company Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Case 79 of 2013
Procedural Posture
Civil Suit / Interlocutory Application (injunction) Ruling
Outcome
Interlocutory injunction partially granted; status quo to be maintained for three months.
Judges
MM Kasango
Legal Topics
Landlord Tenant Disputes, Injunctive Relief, Mesne Profits, Holding Over Tenancy
Source Language
en
Land and Property Civil Procedure Landlord Tenant Disputes Injunctive Relief Mesne Profits Holding Over Tenancy

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Lucy N. Momanyi t/a L. N. Momanyi & Company Advocates

Plaintiff

Joel Ombati Nyamweya

Defendant

Kenya Power & Lighting Company Limited

Defendant

Procedural Posture

Civil Suit / Interlocutory Application (injunction) Ruling

  1. 1 Whether the plaintiff is entitled to an injunction restraining the defendants from blocking access to her office and interfering with her possession.
  2. 2 Whether the plaintiff is a trespasser or a holding over tenant after expiry of the lease.
  3. 3 Whether the defendants' actions in blockading the plaintiff's office were lawful.

Ratio Decidendi

The court found that while the plaintiff's lease had expired in July 2012, and there was evidence of rent arrears, the defendants were not justified in blockading the plaintiff's office without a court order. The court rejected the plaintiff's objection to the 1st defendant's authority to swear the affidavit, holding that the 1st defendant's statement of authority sufficed unless challenged by the 2nd defendant. The court emphasized that at the interlocutory stage, it should not resolve disputed facts but maintain the status quo to prevent injustice. Accordingly, the court ordered the maintenance of the status quo for three months, during which the plaintiff must continue paying rent, and...

Court Disposition

Interlocutory injunction partially granted; status quo to be maintained for three months.

Orders

  • Defendants to maintain status quo for three months regarding the plaintiff's occupation of the 7th floor office at Electricity House, Msa Block XXIV/20, Nkrumah Road, Mombasa.
  • Plaintiff to continue paying rent when due during this period.