[2018] KEELRC 2403 (KLR)

[2018] KEELRC 2403 (KLR)

The court found that the contract between the parties expressly required disputes arising out of or relating to the contract, including termination, to be referred first to the Dispute Resolution Tribunal of the Kenya Premier League. The claimant failed to provide documentary evidence that he had referred the...

Source-derived case information.

Citation
[2018] KEELRC 2403 (KLR)
Parties
Claimant: Luke Ochieng Owino; Respondent: Gor Mahia F.C.
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nairobi
Jurisdiction
Kenya
Case Number
Cause 660 of 2017
Procedural Posture
Employment Cause / Ruling on Preliminary Objection
Outcome
cause stayed pending exhaustion of dispute resolution mechanisms
Judges
MSA Makhandia
Legal Topics
Unfair Termination, Contractual Dispute Resolution, Jurisdiction of Court
Source Language
en
Employment and Labour Unfair Termination Contractual Dispute Resolution Jurisdiction of Court

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2
Sign in to unlock

Parties

Luke Ochieng Owino

Claimant

Gor Mahia F.C.

Respondent

Procedural Posture

Employment Cause / Ruling on Preliminary Objection

  1. 1 Whether the Employment and Labour Relations Court has jurisdiction to hear the dispute before exhaustion of the contractually agreed dispute resolution mechanisms.
  2. 2 Whether the claimant had exhausted the dispute resolution mechanisms provided under the Kenya Premier League Contract of Employment for Footballers.

Ratio Decidendi

The court found that the contract between the parties expressly required disputes arising out of or relating to the contract, including termination, to be referred first to the Dispute Resolution Tribunal of the Kenya Premier League. The claimant failed to provide documentary evidence that he had referred the dispute to the appropriate body or exhausted the agreed mechanisms. Therefore, the court held that it lacked jurisdiction to entertain the matter until the claimant had complied with the dispute resolution procedure stipulated in the contract. The proceedings were stayed pending exhaustion of those mechanisms.

Court Disposition

cause stayed pending exhaustion of dispute resolution mechanisms

Orders