[2001] KEHC 156 (KLR)

[2001] KEHC 156 (KLR)

The court found that the Defendant had properly fixed the completion date by written notice in accordance with the contract, and the Plaintiff failed to complete within the stipulated period. The Plaintiff's argument of oral variation was unsupported by evidence and contradicted by her own admissions. The Defendant...

Source-derived case information.

Citation
[2001] KEHC 156 (KLR)
Parties
Plaintiff: Margaret Alividza; Defendant: L.Z. Engineering Construction Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
? 417 of 1989
Procedural Posture
Civil Case / Judgment
Outcome
plaintiff's suit dismissed with costs
Legal Topics
Specific Performance, Contract Rescission, Completion Notice, Variation of Contract, Sale of Land, Remedies for Breach
Source Language
en
Land and Property Commercial and Corporate Specific Performance Contract Rescission Completion Notice Variation of Contract Sale of Land Remedies for Breach

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Margaret Alividza

Plaintiff

L.Z. Engineering Construction Ltd

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the date of completion of the sale had been fixed by the time the Defendant cancelled the Sale Agreement.
  2. 2 Whether the Plaintiff was willing and is still ready and willing to fulfill all the obligations under the said agreement.
  3. 3 Whether the Defendant served on the Plaintiff notice requiring completion of sale, and if so, whether the Plaintiff failed to complete within the time fixed for completion.

Ratio Decidendi

The court found that the Defendant had properly fixed the completion date by written notice in accordance with the contract, and the Plaintiff failed to complete within the stipulated period. The Plaintiff's argument of oral variation was unsupported by evidence and contradicted by her own admissions. The Defendant was entitled under clause 11 to rescind the agreement upon the Plaintiff's default. As the Plaintiff could not fulfill her obligations within the fixed period, she was not entitled to specific performance or any other remedy. The Defendant's rescission was lawful, and the Plaintiff's suit was dismissed with costs.

Court Disposition

plaintiff's suit dismissed with costs

Orders

  • The Plaintiff's suit is dismissed with costs to the Defendant.