[2016] KEELC 495 (KLR)

[2016] KEELC 495 (KLR)

The court found that the defendant constructed the house, well, and ablution block on the plaintiff's land with the plaintiff's knowledge and consent, pursuant to an agreement that the defendant would be compensated with land or money equivalent to the value of the improvements. The plaintiff's subsequent denial of...

Source-derived case information.

Citation
[2016] KEELC 495 (KLR)
Parties
Plaintiff: Mark Mathenge Gikonyo; Defendant: Raphael Githinji
Court
Environment and Land Court
Court Station
Environment and Land Court at Kitale
Jurisdiction
Kenya
Case Number
Land Case 6 “C” of 2013
Procedural Posture
Land Case / Judgment
Outcome
Plaintiff's suit dismissed; defendant's counter-claim allowed.
Judges
EO Obaga
Legal Topics
Ownership Dispute, Counter Claim, Constructive Trust, Injunctive Relief, Valuation of Improvements
Source Language
en
Land and Property Ownership Dispute Counter Claim Constructive Trust Injunctive Relief Valuation of Improvements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mark Mathenge Gikonyo

Plaintiff

Raphael Githinji

Defendant

Procedural Posture

Land Case / Judgment

  1. 1 Whether the defendant constructed a house on the plaintiff's land with the plaintiff's permission or knowledge.
  2. 2 Whether there was an agreement entitling the defendant to land or monetary compensation equivalent to the value of the house constructed.
  3. 3 Whether the plaintiff is entitled to a permanent injunction and demolition of the house.

Ratio Decidendi

The court found that the defendant constructed the house, well, and ablution block on the plaintiff's land with the plaintiff's knowledge and consent, pursuant to an agreement that the defendant would be compensated with land or money equivalent to the value of the improvements. The plaintiff's subsequent denial of the agreement was not credible, given the evidence of witnesses, the written agreement, and the plaintiff's conduct during the construction and valuation. The court held that it would be inequitable to order demolition or grant injunctive relief to the plaintiff, who had acquiesced to the defendant's actions. The defendant was entitled to monetary compensation for the value of...

Court Disposition

Plaintiff's suit dismissed; defendant's counter-claim allowed.

Orders

  • Plaintiff's claim is dismissed with costs to the defendant.
  • Judgment entered for the defendant in terms of prayer (a) of the counter-claim for Kshs.2,100,000.