[2018] KEELC 2557 (KLR)

[2018] KEELC 2557 (KLR)

The court found that the Plaintiff had paid the full purchase price as per the original agreement, albeit outside the stipulated 90-day period. The defendant accepted these late payments and also accepted a penalty for late payment, thereby waiving its right to insist on strict compliance with the payment timeline....

Source-derived case information.

Citation
[2018] KEELC 2557 (KLR)
Parties
Plaintiff: Mary Wanjiru Ndegwa; Defendant: Wandemi Developers Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 666 of 2012
Procedural Posture
Environment and Land Court Suit / Judgment
Outcome
Judgment for the Plaintiff; specific performance and injunction granted.
Legal Topics
Specific Performance, Sale of Land, Contract Variation, Waiver and Estoppel, Rescission of Contract
Source Language
en
Land and Property Civil Procedure Specific Performance Sale of Land Contract Variation Waiver and Estoppel Rescission of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Mary Wanjiru Ndegwa

Plaintiff

Wandemi Developers Limited

Defendant

Procedural Posture

Environment and Land Court Suit / Judgment

  1. 1 Did the Plaintiff clear payment of the purchase price?
  2. 2 Was there an agreement between parties to enhance the purchase price to Kshs.5,000,000/-?
  3. 3 What was the effect of the Plaintiff making payments outside the 90 days granted in the agreement?

Ratio Decidendi

The court found that the Plaintiff had paid the full purchase price as per the original agreement, albeit outside the stipulated 90-day period. The defendant accepted these late payments and also accepted a penalty for late payment, thereby waiving its right to insist on strict compliance with the payment timeline. There was no evidence of a mutually agreed variation to increase the purchase price. The defendant's subsequent demands for additional sums and attempt to rescind the agreement were unjustified and amounted to an attempt to extract a higher price contrary to the binding contract. The Plaintiff was therefore entitled to specific performance, as she had fulfilled her obligations...

Court Disposition

Judgment for the Plaintiff; specific performance and injunction granted.

Orders

  • A permanent injunction restraining the defendant from transferring or disposing of LR No. 27981/12 to any person other than the Plaintiff.
  • An order of specific performance directing the defendant to transfer LR No. 27981/12 to the Plaintiff.