[2017] KEHC 9464 (KLR)

[2017] KEHC 9464 (KLR)

The court found that the guarantees in question were autonomous and did not expressly require proof of breach or a statement of breach as a condition for payment. The guarantees were not conditional but rather on-demand, and the court could not imply terms not present in the guarantee documents. The plaintiff failed...

Source-derived case information.

Citation
[2017] KEHC 9464 (KLR)
Parties
Plaintiff: Mehta Electricals Limited; Defendant: I & M Bank Limited; Defendant: Synohydro Corporation Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 55 of 2017
Procedural Posture
Civil Suit / Ruling on Application for Temporary Prohibitive Injunction
Outcome
application dismissed
Legal Topics
Demand Guarantees, Advance Payment Guarantees, Injunctive Relief, Subcontractor Rights, Autonomy of Guarantees
Source Language
en
Commercial and Corporate Banking and Finance Demand Guarantees Advance Payment Guarantees Injunctive Relief Subcontractor Rights Autonomy of Guarantees

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Mehta Electricals Limited

Plaintiff

I & M Bank Limited

Defendant

Synohydro Corporation Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Application for Temporary Prohibitive Injunction

  1. 1 Whether the plaintiff is entitled to a temporary injunction restraining the 1st defendant from making payment to the 2nd defendant under the advance payment guarantees.
  2. 2 Whether the guarantees in question are conditional or on-demand guarantees.
  3. 3 Whether the 2nd defendant is required to demonstrate breach of subcontract by the plaintiff before calling up the guarantees.

Ratio Decidendi

The court found that the guarantees in question were autonomous and did not expressly require proof of breach or a statement of breach as a condition for payment. The guarantees were not conditional but rather on-demand, and the court could not imply terms not present in the guarantee documents. The plaintiff failed to demonstrate that the guarantees contained an arbitration agreement or that the bank was party to the subcontract's arbitration clause. There was no evidence of fraud, misrepresentation, or special equities to restrain enforcement of the guarantees. Since the subcontract was not being performed and the plaintiff was holding the bulk of the advance payment, there was no legal...

Court Disposition

application dismissed

Orders

  • The application dated 6th February 2017 is dismissed.
  • The plaintiff shall pay costs to the defendants.