https://new.kenyalaw.org/akn/ke/judgment/keca/2026/926

https://new.kenyalaw.org/akn/ke/judgment/keca/2026/926

The appellant failed to prove a contractual entitlement to the claimed outstanding sum because the contract fixed the initial price, required written mutual agreement for any variation, and required written approval for extensions of time; no evidence showed lawful variation of the contract sum or further approved...

Source-derived case information.

Citation
[2026] KECA 926 (KLR)
Parties
Appellant: Mistry Javda Parbat & Company Limited; Respondent: National Oil Corporation of Kenya
Court
Court of Appeal
Jurisdiction
Kenya
Case Number
Civil Appeal E031 of 2024
Procedural Posture
Civil Appeal From High Court Judgment in a Construction Contract Dispute / Judgment on First Appeal
Outcome
Appeal dismissed with costs to the respondent
Judges
["AK Murgor", "KI Laibuta", "GW Ngenye-Macharia"]
Legal Topics
Interpretation of Construction Contract Terms, Payment Under Final Certificate, Extension of Time in Construction Contracts, Burden and Standard of Proof, Special Damages and Proof, Costs and Taxation
Source Language
en
Civil Procedure Contract Law Construction Law Evidence Law Interpretation of Construction Contract Terms Payment Under Final Certificate Extension of Time in Construction Contracts Burden and Standard of Proof +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 20 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Mistry Javda Parbat & Company Limited

Appellant

National Oil Corporation of Kenya

Respondent

Procedural Posture

Civil Appeal From High Court Judgment in a Construction Contract Dispute / Judgment on First Appeal

  1. 1 Whether the appellant proved entitlement to Kshs.19,840,912.20 under the construction contract
  2. 2 Whether the contract sum could be varied from Kshs.41,668,380.75 to Kshs.68,637,211.55 without written mutual agreement
  3. 3 Whether the appellant proved approval of extension(s) of time beyond the initial approved extension

Ratio Decidendi

The appellant failed to prove a contractual entitlement to the claimed outstanding sum because the contract fixed the initial price, required written mutual agreement for any variation, and required written approval for extensions of time; no evidence showed lawful variation of the contract sum or further approved extensions beyond the limited extension granted. On the evidence, the respondent had in fact overpaid the appellant, so the appeal failed.

Court Disposition

Appeal dismissed with costs to the respondent

Orders

  • The appeal is dismissed.
  • The High Court judgment of 17 July 2023 is upheld.