[2023] KEELC 20775 (KLR)

[2023] KEELC 20775 (KLR)

The court held that although the suit was framed as one for trespass, it concerned a special type of trespass relating to the laying of electricity poles, which was specifically addressed by the dispute resolution mechanism under the Energy Act, 2006. At the time the suit was filed in 2018, the Energy Act, 2019 was...

Source-derived case information.

Citation
[2023] KEELC 20775 (KLR)
Parties
Appellant: Charles Morira Mochere; Respondent: Kenya Power & Lighting Company Limited; Respondent: Rwathia Distributors Company Limited; Respondent: Timothy Erick Onyonka
Court
Environment and Land Court
Court Station
Environment and Land Court at Kisii
Jurisdiction
Kenya
Case Number
Environment and Land Appeal 4 of 2023
Procedural Posture
Environment and Land Appeal / Judgment on Appeal Against Preliminary Objection on Jurisdiction
Outcome
appeal dismissed
Judges
M Sila
Legal Topics
Trespass to Land, Electricity Infrastructure Disputes, Statutory Dispute Resolution, Jurisdiction of Magistrates Court
Source Language
en
Land and Property Administrative Law Trespass to Land Electricity Infrastructure Disputes Statutory Dispute Resolution Jurisdiction of Magistrates Court

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Charles Morira Mochere

Appellant

Kenya Power & Lighting Company Limited

Respondent

Rwathia Distributors Company Limited

Respondent

Timothy Erick Onyonka

Respondent

Procedural Posture

Environment and Land Appeal / Judgment on Appeal Against Preliminary Objection on Jurisdiction

  1. 1 Whether the Magistrate's Court had jurisdiction to hear a suit for trespass arising from the laying of electricity poles on private land.
  2. 2 Whether the appellant was required to exhaust the dispute resolution mechanisms under the Energy Act, 2006 before approaching the court.
  3. 3 Whether the provisions of the Energy Act, 2019 applied retrospectively to a suit filed in 2018.

Ratio Decidendi

The court held that although the suit was framed as one for trespass, it concerned a special type of trespass relating to the laying of electricity poles, which was specifically addressed by the dispute resolution mechanism under the Energy Act, 2006. At the time the suit was filed in 2018, the Energy Act, 2019 was not in force and could not apply retrospectively. The Energy Act, 2006 provided that disputes regarding the laying of electric supply lines on private land should first be referred to the Energy Regulatory Commission, with a right of appeal to the Energy Tribunal. The appellant failed to demonstrate that this statutory mechanism was unavailable or ineffective. Therefore, the...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the 1st respondent.