[2010] KEHC 3521 (KLR)

[2010] KEHC 3521 (KLR)

The court found that the applicant established a prima facie case by demonstrating that the contract period had lapsed and the works remained incomplete, with both parties blaming each other for the delay. However, the applicant failed to show that damages would not be an adequate remedy, as the sums paid and work...

Source-derived case information.

Citation
[2010] KEHC 3521 (KLR)
Parties
Plaintiff: Mohamed Yerrow Duba t/a Bonny Construction Investments; Defendant: Peter M. Kimuyu t/a Perma Structural Engineering Co.
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 103 of 2008
Procedural Posture
Civil Suit / Ruling on Interlocutory Injunction Application
Outcome
Interlocutory injunction granted with conditions.
Judges
DO Ohungo
Legal Topics
Interlocutory Injunctions, Breach of Contract, Construction Disputes, Specific Performance, Quantification of Work
Source Language
en
Civil Procedure Commercial and Corporate Interlocutory Injunctions Breach of Contract Construction Disputes Specific Performance Quantification of Work

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Mohamed Yerrow Duba t/a Bonny Construction Investments

Plaintiff

Peter M. Kimuyu t/a Perma Structural Engineering Co.

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Injunction Application

  1. 1 Whether the applicant is entitled to a temporary injunction restraining the respondent from entering or interfering with the construction site at Kilifi Water Tank pending determination of the suit.
  2. 2 Whether the applicant has established a prima facie case with a probability of success.
  3. 3 Whether damages would be an adequate remedy for the applicant.

Ratio Decidendi

The court found that the applicant established a prima facie case by demonstrating that the contract period had lapsed and the works remained incomplete, with both parties blaming each other for the delay. However, the applicant failed to show that damages would not be an adequate remedy, as the sums paid and work done were quantifiable. The balance of convenience favored the applicant, given the breakdown in the relationship and the need to complete the public water project. The court held that it was more convenient to restrain the respondent from further activities on site, pending an independent assessment of the work done, after which the applicant could engage another contractor to...

Court Disposition

Interlocutory injunction granted with conditions.

Orders

  • An injunction is issued restraining the respondent, his servants, agents, or employees from entering or interfering with the Kilifi Water Tank construction site.
  • The parties shall agree on an independent assessor within seven days to assess and quantify the work done by the respondent.