[2012] KEHC 1345 (KLR)

[2012] KEHC 1345 (KLR)

The court found that while a loan agreement existed between the parties, the plaintiff failed to prove full compliance with the pre-disbursement conditions, specifically the provision of shareholder guarantees and a board resolution authorizing the borrowing. The plaintiff did not produce the loan agreement or...

Source-derived case information.

Citation
[2012] KEHC 1345 (KLR)
Parties
Plaintiff: Molo Mount Mineral Water Limited; Defendant: Industrial Development Bank Limited
Court
High Court
Court Station
High Court at Nakuru
Jurisdiction
Kenya
Case Number
Civil Case 113 of 2004
Procedural Posture
Civil Case / Judgment
Outcome
suit dismissed with costs to the defendant
Judges
RPV Wendoh
Legal Topics
Loan Agreements, Breach of Contract, Pre Disbursement Conditions, Damages for Breach, Corporate Authority, Burden of Proof
Source Language
en
Commercial and Corporate Banking and Finance Civil Procedure Loan Agreements Breach of Contract Pre Disbursement Conditions Damages for Breach Corporate Authority +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Molo Mount Mineral Water Limited

Plaintiff

Industrial Development Bank Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether there was an affidavit to verify the plaint.
  2. 2 Whether there existed a contract between the parties.
  3. 3 Whether the plaintiff performed its obligations under the contract.

Ratio Decidendi

The court found that while a loan agreement existed between the parties, the plaintiff failed to prove full compliance with the pre-disbursement conditions, specifically the provision of shareholder guarantees and a board resolution authorizing the borrowing. The plaintiff did not produce the loan agreement or sufficient evidence of performance, and failed to specifically plead and prove damages or loss of earnings. The court held that general damages are not awardable for breach of contract under Kenyan law, and that the burden of proof rested with the plaintiff, who failed to discharge it. Consequently, the defendant was justified in terminating the agreement, and the plaintiff's suit...

Court Disposition

suit dismissed with costs to the defendant

Orders

  • The plaintiff's suit is dismissed.