[2025] KEELC 3238 (KLR)

[2025] KEELC 3238 (KLR)

The court found that the plaintiff failed to provide evidence that the defendant or its staff erected the electric poles or supplied electricity to the suit property. The burden of proof lay with the plaintiff, who did not produce photographs, witness identification, or other documentation linking the defendant to...

Source-derived case information.

Citation
[2025] KEELC 3238 (KLR)
Parties
Plaintiff: Mombasa Auto Spares Limited; Defendant: Kenya Power & Lighting Company Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 162 of 2015
Procedural Posture
Environment and Land Case / Judgment
Outcome
Plaintiff's suit dismissed; no order as to costs. Ancillary orders issued regarding investigation and disconnection of illegal electricity connections.
Judges
FM Njoroge
Legal Topics
Trespass to Land, Injunctive Relief, Burden of Proof, Illegal Electricity Connections
Source Language
en
Land and Property Civil Procedure Trespass to Land Injunctive Relief Burden of Proof Illegal Electricity Connections

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mombasa Auto Spares Limited

Plaintiff

Kenya Power & Lighting Company Limited

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the defendant supplied electricity to the plaintiff's land without consent.
  2. 2 Whether the defendant trespassed on the plaintiff's property by erecting electric poles.
  3. 3 Whether the plaintiff is entitled to injunctive and declaratory reliefs against the defendant.

Ratio Decidendi

The court found that the plaintiff failed to provide evidence that the defendant or its staff erected the electric poles or supplied electricity to the suit property. The burden of proof lay with the plaintiff, who did not produce photographs, witness identification, or other documentation linking the defendant to the alleged acts. The defendant's denial and evidence that it did not construct the lines or supply power were not rebutted by the plaintiff. Consequently, the plaintiff's claim against the defendant could not succeed. However, the court recognized the existence of illegal electricity connections on the property and ordered procedural steps for the plaintiff to lodge a formal...

Court Disposition

Plaintiff's suit dismissed; no order as to costs. Ancillary orders issued regarding investigation and disconnection of illegal electricity connections.

Orders

  • Plaintiff to lodge a formal complaint with the defendant within 7 days regarding illegal power connections.
  • Defendant to document and verify illegal connections within 30 days of receiving the complaint and supply data to the plaintiff.