[2024] KEHC 14213 (KLR)

[2024] KEHC 14213 (KLR)

The court found that the plaintiff and defendant entered into a valid construction contract (JBC Agreement) for the building of maisonettes, with clear terms on payment upon completion and issuance of a certificate of completion. The plaintiff completed the works, obtained the certificate of completion on 31st...

Source-derived case information.

Citation
[2024] KEHC 14213 (KLR)
Parties
Plaintiff: Monaco Engineering Limited; Defendant: Munywe Investment Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 62 of 2019
Procedural Posture
Civil Case / Ruling on Merits After Full Hearing
Outcome
judgment for the plaintiff
Judges
AN Ongeri
Legal Topics
Construction Contracts, Specific Performance, Contractual Interest, Final Account Disputes
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Specific Performance Contractual Interest Final Account Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Monaco Engineering Limited

Plaintiff

Munywe Investment Limited

Defendant

Procedural Posture

Civil Case / Ruling on Merits After Full Hearing

  1. 1 Whether the plaintiff is entitled to the sum of Kshs. 29,964,789.60 as agreed payment as at 31/8/2017.
  2. 2 Whether the plaintiff is entitled to interest for delayed payment and at what rate.
  3. 3 Whether the property known as Maisonettes for Munywe Investment Ltd in Sigona LR No. Sigona/422 (Part) – Kikuyu should be attached to satisfy the judgment sum.

Ratio Decidendi

The court found that the plaintiff and defendant entered into a valid construction contract (JBC Agreement) for the building of maisonettes, with clear terms on payment upon completion and issuance of a certificate of completion. The plaintiff completed the works, obtained the certificate of completion on 31st August 2017, and raised invoices for payment. The defendant failed to pay the full contract sum, leaving an outstanding balance of Kshs. 29,964,789.60. The defendant did not adduce any evidence or call witnesses to controvert the plaintiff's case. While the defendant argued that the final account was not verified by the quantity surveyor as required by the contract, the court found...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered in favour of the plaintiff against the defendant in the sum of Kshs. 29,964,789.60.
  • Interest awarded at court rates (12% p.a.) from 31st August 2017 until payment in full.