[2009] KEHC 686 (KLR)

[2009] KEHC 686 (KLR)

The court found that the plaintiff had proved, on a balance of probabilities, that it was not paid the sum of Ksh. 1,234,903.85 for construction work performed under the contract with the defendant. The plaintiff's evidence, including the valuation report by PW2, was uncontroverted as the defendant did not adduce...

Source-derived case information.

Citation
[2009] KEHC 686 (KLR)
Parties
Plaintiff: Mortaj Construction Limited; Defendant: Red Bull Energy Drink Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 1879 of 2000
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Judges
FI Koome
Legal Topics
Construction Contracts, Special Damages, Proof of Claims, Termination of Contract
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Special Damages Proof of Claims Termination of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mortaj Construction Limited

Plaintiff

Red Bull Energy Drink Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff proved entitlement to special damages for unpaid construction work.
  2. 2 Whether the plaintiff is entitled to general damages for confiscated tools, equipment, and materials.
  3. 3 Whether the defendant's termination of the contract was justified and whether any counterclaim was established.

Ratio Decidendi

The court found that the plaintiff had proved, on a balance of probabilities, that it was not paid the sum of Ksh. 1,234,903.85 for construction work performed under the contract with the defendant. The plaintiff's evidence, including the valuation report by PW2, was uncontroverted as the defendant did not adduce any evidence to challenge the claim or the report. The court held that special damages must be specifically pleaded and strictly proved, which the plaintiff did in respect of the unpaid contract sum. However, the plaintiff failed to prove the value of confiscated tools, equipment, and materials, and no evidence was adduced to support the claim for general damages for their...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the plaintiff for Ksh. 1,234,903.85.
  • Plaintiff awarded costs of the suit.