[2009] KEHC 4017 (KLR)

[2009] KEHC 4017 (KLR)

The court found that the plaintiff's cause of action did not arise at the time of delivery of goods in June 1995, but rather on 10th September 1998, when the defendant, through its advocate, expressly repudiated the barter agreement and acknowledged the plaintiff's entitlement to collect its goods. This letter...

Source-derived case information.

Citation
[2009] KEHC 4017 (KLR)
Parties
Plaintiff: Motex Knitwear Limited; Defendant: Gopitex Knitwear Mills Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 834 of 2002
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Judges
CJ Kendagor
Legal Topics
Barter Agreements, Contractual Liability, Limitation of Actions, Acknowledgment of Debt
Source Language
en
Commercial and Corporate Civil Procedure Barter Agreements Contractual Liability Limitation of Actions Acknowledgment of Debt

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Motex Knitwear Limited

Plaintiff

Gopitex Knitwear Mills Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff's claim is statute barred under the Limitation of Actions Act.
  2. 2 Whether the plaintiff has proved its claim for the value of goods delivered under the barter agreement.

Ratio Decidendi

The court found that the plaintiff's cause of action did not arise at the time of delivery of goods in June 1995, but rather on 10th September 1998, when the defendant, through its advocate, expressly repudiated the barter agreement and acknowledged the plaintiff's entitlement to collect its goods. This letter constituted a written acknowledgment of debt within the meaning of sections 23(3) and 24(1) of the Limitation of Actions Act, thereby resetting the limitation period. The defendant's failure to fulfill its part of the agreement or return the goods rendered it liable for the value of the goods delivered. The defendant's failure to call any evidence left the plaintiff's case...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the plaintiff against the defendant in the sum of Kshs.6,062,198/- together with interest at court rates from the date of filing suit to the date of full payment.