[2005] KEHC 290 (KLR)

[2005] KEHC 290 (KLR)

The court found that the applicant failed to demonstrate a prima facie case with a probability of success to justify remaining in possession of the suit premises pending arbitration. The court held that damages would be an adequate remedy if the applicant ultimately succeeded in the arbitration. The court also noted...

Source-derived case information.

Citation
[2005] KEHC 290 (KLR)
Parties
Plaintiff: Mugoya Construction & Engineering Limited; Defendant: National Social Security Fund Board of Trustees (N.S.S.F.); Defendant: Symbion International
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 59 of 2005
Procedural Posture
Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration
Outcome
application dismissed with costs to the 1st and 2nd respondents, subject to applicant being allowed two weeks to take measurements.
Legal Topics
Interim Injunctions, Arbitration Clauses, Breach of Contract, Specific Performance, Remedies for Breach, Contract Termination
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Interim Injunctions Arbitration Clauses Breach of Contract Specific Performance Remedies for Breach +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Mugoya Construction & Engineering Limited

Plaintiff

National Social Security Fund Board of Trustees (N.S.S.F.)

Defendant

Symbion International

Defendant

Procedural Posture

Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration

  1. 1 Whether the applicant is entitled to interim injunctive relief to remain in possession of the suit premises pending arbitration.
  2. 2 Whether the applicant has established a prima facie case with a probability of success to warrant the orders sought.
  3. 3 Whether damages would be an adequate remedy for the applicant if the contract was wrongly terminated.

Ratio Decidendi

The court found that the applicant failed to demonstrate a prima facie case with a probability of success to justify remaining in possession of the suit premises pending arbitration. The court held that damages would be an adequate remedy if the applicant ultimately succeeded in the arbitration. The court also noted that the applicant had not come to court with clean hands, as it appeared to be seeking to delay the appointment of an arbitrator and retain possession of the site without progressing the works. The court concluded that allowing the applicant to remain on the premises would cause injustice to the respondents, as no work was ongoing and the completed work would deteriorate....

Court Disposition

application dismissed with costs to the 1st and 2nd respondents, subject to applicant being allowed two weeks to take measurements.

Orders

  • The application for interim injunctive relief is dismissed.
  • The applicant is granted two weeks from the date of the ruling to take measurements on the suit premises.