[2019] KEELC 938 (KLR)

[2019] KEELC 938 (KLR)

The court found that while the respondent's explanation for the delay in prosecuting the suit was plausible, the respondent failed to notify the applicant or the court of the difficulties encountered, which could have justified the delay. The court held that the applicant was justified in filing the application for...

Source-derived case information.

Citation
[2019] KEELC 938 (KLR)
Parties
Plaintiff: Mumwanjesyi Development Ltd; Defendant: Mbarak Mohamed Ali
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case 60 of 2016
Procedural Posture
Dismissal Application / Ruling on Application for Dismissal for Want of Prosecution
Outcome
Application for dismissal for want of prosecution conditionally declined; suit to proceed if costs paid within 14 days, otherwise suit stands dismissed.
Legal Topics
Dismissal for Want of Prosecution, Delay in Prosecution, Injunctive Relief, Land Encroachment
Source Language
en
Civil Procedure Land and Property Dismissal for Want of Prosecution Delay in Prosecution Injunctive Relief Land Encroachment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mumwanjesyi Development Ltd

Plaintiff

Mbarak Mohamed Ali

Defendant

Procedural Posture

Dismissal Application / Ruling on Application for Dismissal for Want of Prosecution

  1. 1 Whether the suit should be dismissed for want of prosecution due to inactivity for over two years.
  2. 2 Whether the respondent's explanation for delay constitutes sufficient cause to avoid dismissal.
  3. 3 Whether costs should be awarded to the applicant for bringing the application.

Ratio Decidendi

The court found that while the respondent's explanation for the delay in prosecuting the suit was plausible, the respondent failed to notify the applicant or the court of the difficulties encountered, which could have justified the delay. The court held that the applicant was justified in filing the application for dismissal. However, in the interest of justice, the court allowed the respondent an opportunity to proceed with the case, subject to the payment of thrown away costs to the applicant within 14 days. Failure to pay the costs would result in the suit being dismissed for want of prosecution with costs to the applicant.

Court Disposition

Application for dismissal for want of prosecution conditionally declined; suit to proceed if costs paid within 14 days, otherwise suit stands dismissed.

Orders

  • Respondent to pay Kshs. 10,000 as thrown away costs to the applicant within 14 days.
  • If costs are not paid within 14 days, the suit stands dismissed for want of prosecution with costs to the applicant.