The court found that the Petitioner had established a constitutional controversy and met the procedural threshold for a constitutional petition. The evidence showed that the Respondents, in the course of upgrading a public road, constructed a culvert that diverted storm water into the Petitioner’s land, causing...

Source-derived case information.

Citation
[2023] KEELC 21195 (KLR)
Parties
Applicant: Edward Mureka; Respondent: Kenya Rural Roads Authority; Respondent: Resident Engineer Musikoma-Mungatsi Mateka Road; Respondent: Cabinet Secretary in Charge of the Ministry of Transport; Respondent: Attorney General
Court
Environment and Land Court
Court Station
Environment and Land Court at Bungoma
Jurisdiction
Kenya
Case Number
Environment & Land Petition E001 of 2022
Procedural Posture
Constitutional Petition / Judgment
Outcome
Petition allowed in part; declarations granted; general damages awarded; order for remedial works; costs to Petitioner.
Judges
EC Cherono
Legal Topics
Compulsory Acquisition, Right to Property, Trespass, Fair Administrative Action, Damages for Trespass, Public Projects
Source Language
en
Land and Property Constitutional Law Civil Procedure Compulsory Acquisition Right to Property Trespass Fair Administrative Action Damages for Trespass +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 18 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Edward Mureka

Applicant

Kenya Rural Roads Authority

Respondent

Resident Engineer Musikoma-Mungatsi Mateka Road

Respondent

Cabinet Secretary in Charge of the Ministry of Transport

Respondent

Attorney General

Respondent

Procedural Posture

Constitutional Petition / Judgment

  1. 1 Whether the petition raises a constitutional controversy and meets the constitutional threshold.
  2. 2 Whether the Petitioner has proved breach of his constitutional rights as set out in the petition against the Respondents jointly and severally.
  3. 3 What reliefs, if any, is the Petitioner entitled to under the circumstances.

Ratio Decidendi

The court found that the Petitioner had established a constitutional controversy and met the procedural threshold for a constitutional petition. The evidence showed that the Respondents, in the course of upgrading a public road, constructed a culvert that diverted storm water into the Petitioner’s land, causing flooding and deprivation of enjoyment of property. The Respondents failed to take remedial action or follow due process for compulsory acquisition or compensation. The court held that the Respondents' actions were unfair, unlawful, and unconstitutional, violating the Petitioner’s rights under Articles 40 and 47 of the Constitution. However, the court found no evidence of actual...

Court Disposition

Petition allowed in part; declarations granted; general damages awarded; order for remedial works; costs to Petitioner.

Orders

  • A declaration that the Petitioner is the lawful proprietor of L.R E. Bukusu/S. Kanduyi/21287.
  • A declaration that the Respondents' actions in seeking to curtail, undermine and/or deprive the Petitioner of rights to the property without just cause and prompt and adequate compensation is unfair, unlawful and unconstitutional.