[2023] KEHC 17852 (KLR)

[2023] KEHC 17852 (KLR)

The court found that although the contract agreement was not signed by both parties, a binding contract could still exist if there was offer, acceptance, and consideration. However, the Plaintiff failed to provide persuasive evidence to prove the value of additional works, the claim for unpaid sums, or the value of...

Source-derived case information.

Citation
[2023] KEHC 17852 (KLR)
Parties
Plaintiff: Haggington Malindi Mwangema T/A Mwangemi General Contractors; Defendant: Attorney General; Defendant: Mombasa Technical Training Institute
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 155 of 2006
Procedural Posture
Civil Suit / Judgment
Outcome
Both the Plaintiff's claim and the Defendants' counterclaim are dismissed.
Judges
DO Chepkwony
Legal Topics
Breach of Contract, Construction Contracts, Burden of Proof, Damages Assessment
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Burden of Proof Damages Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Haggington Malindi Mwangema T/A Mwangemi General Contractors

Plaintiff

Attorney General

Defendant

Mombasa Technical Training Institute

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the contract between the Plaintiff and the Government for construction of student hostels is enforceable.
  2. 2 Whether the Plaintiff's claim for unpaid sums and damages is merited.
  3. 3 Whether the Defendants' counterclaim for liquidated damages and completion costs is merited.

Ratio Decidendi

The court found that although the contract agreement was not signed by both parties, a binding contract could still exist if there was offer, acceptance, and consideration. However, the Plaintiff failed to provide persuasive evidence to prove the value of additional works, the claim for unpaid sums, or the value of materials left on site. The Plaintiff also did not substantiate the claim for works done by the electrical sub-contractor. The claim for general damages based on inflation was deemed speculative and not a proximate consequence of breach. The Defendants' counterclaim was also dismissed for lack of supporting evidence. Both the Plaintiff and Defendants failed to meet the required...

Court Disposition

Both the Plaintiff's claim and the Defendants' counterclaim are dismissed.

Orders

  • The Plaintiff's suit is dismissed.
  • The Defendants' counterclaim is dismissed.