[2024] KEELC 1580 (KLR)

[2024] KEELC 1580 (KLR)

The court found that the existence of the land sale agreement between the plaintiff and the 1st defendant was not disputed. Despite the defendants' initial denial, their own affidavit admitted that the plaintiff had developed part of the land. The plaintiff demonstrated possession and substantial investment in the...

Source-derived case information.

Citation
[2024] KEELC 1580 (KLR)
Parties
Plaintiff: Nagida Construction & Engineering Company Limited; Defendant: Daniel Matende Oriedo; Defendant: Ernest Kalavu Khavogoi
Court
Environment and Land Court
Court Station
Environment and Land Court at Vihiga
Jurisdiction
Kenya
Case Number
Environment & Land Case E001 of 2024
Procedural Posture
Environment and Land Case / Ruling on Interlocutory Injunction Application
Outcome
Application allowed. Temporary injunction granted.
Judges
E Asati
Legal Topics
Temporary Injunctions, Land Sale Agreements, Possession and Development, Breach of Contract, Balance of Convenience
Source Language
en
Land and Property Civil Procedure Temporary Injunctions Land Sale Agreements Possession and Development Breach of Contract Balance of Convenience

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Nagida Construction & Engineering Company Limited

Plaintiff

Daniel Matende Oriedo

Defendant

Ernest Kalavu Khavogoi

Defendant

Procedural Posture

Environment and Land Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiff has established a prima facie case with a probability of success to warrant a temporary injunction.
  2. 2 Whether the plaintiff would suffer irreparable injury not compensable by damages if the injunction is not granted.
  3. 3 Whether the balance of convenience tilts in favour of granting the injunction.

Ratio Decidendi

The court found that the existence of the land sale agreement between the plaintiff and the 1st defendant was not disputed. Despite the defendants' initial denial, their own affidavit admitted that the plaintiff had developed part of the land. The plaintiff demonstrated possession and substantial investment in the property. The court was satisfied that the plaintiff had established a prima facie case with a probability of success, and that irreparable loss would be suffered if the defendants' actions were not restrained. The balance of convenience favored maintaining the status quo and preserving the plaintiff's interests pending the hearing and determination of the main suit....

Court Disposition

Application allowed. Temporary injunction granted.

Orders

  • Pending hearing and determination of the suit, a temporary injunction is issued restraining the defendants from entering, subdividing by erecting poles, destroying the applicant’s concrete poles and property on land parcel known as Kakamega/cheptulu/1487, now mutated into Kakamega/cheptulu/1894 and 1895.
  • Costs to abide the main suit.