[2023] KEHC 21084 (KLR)

[2023] KEHC 21084 (KLR)

The court found that the respondent failed to set the matter down for hearing within the six months stipulated in the consent order of 7/2/2019, and did not seek an extension before expiry. Although the Water Appeals Board was not constituted, the respondent should have moved the court for extension rather than...

Source-derived case information.

Citation
[2023] KEHC 21084 (KLR)
Parties
Applicant: Nairobi City Water & Sewerage Co Ltd; Respondent: Bibi Properties Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Civil Application 311 of 2017
Procedural Posture
Miscellaneous Civil Application / Ruling on Application for Dismissal for Want of Prosecution and Release of Deposited Funds
Outcome
Application allowed in part; suit deemed dismissed by operation of consent order; funds released to applicant; applicant at liberty to demand unpaid bills; no order as to costs.
Judges
JN Mulwa
Legal Topics
Dismissal for Want of Prosecution, Consent Orders, Release of Deposited Funds, Utility Billing Disputes
Source Language
en
Civil Procedure Commercial and Corporate Dismissal for Want of Prosecution Consent Orders Release of Deposited Funds Utility Billing Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Nairobi City Water & Sewerage Co Ltd

Applicant

Bibi Properties Limited

Respondent

Procedural Posture

Miscellaneous Civil Application / Ruling on Application for Dismissal for Want of Prosecution and Release of Deposited Funds

  1. 1 Whether the suit should be dismissed for want of prosecution due to inaction by the respondent.
  2. 2 Whether the sum of Kshs.419,200 deposited in court should be released to the applicant.
  3. 3 Whether the applicant is entitled to demand payment of outstanding water bills from the respondent.

Ratio Decidendi

The court found that the respondent failed to set the matter down for hearing within the six months stipulated in the consent order of 7/2/2019, and did not seek an extension before expiry. Although the Water Appeals Board was not constituted, the respondent should have moved the court for extension rather than remain inactive. By the time of the application under review, the suit stood dismissed by operation of the consent order and lapse of time. There was thus no competent suit before the court to dismiss. The applicant was entitled to demand payment of all unpaid water bills from the respondent from 16/5/2018, and the sum of Kshs.419,200 deposited in court was to be released to the...

Court Disposition

Application allowed in part; suit deemed dismissed by operation of consent order; funds released to applicant; applicant at liberty to demand unpaid bills; no order as to costs.

Orders

  • The sum of Kshs.419,200 deposited in court is to be released forthwith to the applicant/1st respondent.
  • The applicant/1st respondent is at liberty to demand payment of all unpaid water bills from the respondent from 16/5/2018, taking into account the released sum.