[2023] KEHC 2665 (KLR)

[2023] KEHC 2665 (KLR)

The High Court held that its jurisdiction was limited to questions of law arising from the arbitral award. The court found that the arbitrator did not exceed the scope of reference, as the issue of frustration was within the matters submitted for determination. The court agreed with the arbitrator that participation...

Source-derived case information.

Citation
[2023] KEHC 2665 (KLR)
Parties
Appellant: National Oil Corporation; Respondent: Tinfra Engineering Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Appeal 001 of 2020
Procedural Posture
Commercial Appeal / Judgment
Outcome
Appeal allowed in part; awards for loss of profit and extended preliminaries set aside; each party to bear its own costs.
Judges
DAS Majanja
Legal Topics
Arbitration Awards, Breach of Contract, Damages Assessment, Loss of Profit, Contractual Frustration
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Awards Breach of Contract Damages Assessment Loss of Profit Contractual Frustration

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

National Oil Corporation

Appellant

Tinfra Engineering Limited

Respondent

Procedural Posture

Commercial Appeal / Judgment

  1. 1 Whether the arbitral award contained decisions beyond the scope of reference to arbitration.
  2. 2 Whether the respondent waived its rights under the contract by participating in a subsequent procurement process.
  3. 3 Whether the arbitral tribunal erred in awarding the respondent loss of profit and extended preliminaries.

Ratio Decidendi

The High Court held that its jurisdiction was limited to questions of law arising from the arbitral award. The court found that the arbitrator did not exceed the scope of reference, as the issue of frustration was within the matters submitted for determination. The court agreed with the arbitrator that participation in a subsequent procurement process did not amount to waiver of contractual rights, as waiver required written consent per the contract. However, the court found that the awards for loss of profit and extended preliminaries were not supported by sufficient evidence. Specifically, the claim for loss of profit was not proved with reasonable certainty, as the 40% profit margin...

Court Disposition

Appeal allowed in part; awards for loss of profit and extended preliminaries set aside; each party to bear its own costs.

Orders

  • The award for loss of profit (KES 24,883,985.00) is set aside.
  • The award for extended preliminaries (KES 5,043,571.00) is set aside.