[2025] KEHC 8723 (KLR)

[2025] KEHC 8723 (KLR)

The court found that the Plaintiff had established, on a balance of probabilities, the existence of a contractual relationship with the Defendant, as evidenced by the LPOs and the Defendant's own admissions. The Plaintiff's evidence of services rendered and the amount claimed was unchallenged, as the Defendant...

Source-derived case information.

Citation
[2025] KEHC 8723 (KLR)
Parties
Plaintiff: Stephen Kingara Ndungu t/a Welcome Car Hire And Transport; Defendant: National Water Conservation & Pipeline Corporation
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Case 775 of 2010
Procedural Posture
Commercial Case / Judgment
Outcome
judgment for the plaintiff
Judges
JWW Mong'are
Legal Topics
Contractual Liability, Local Purchase Orders, Burden of Proof, Uncontested Claims
Source Language
en
Commercial and Corporate Civil Procedure Contractual Liability Local Purchase Orders Burden of Proof Uncontested Claims

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Stephen Kingara Ndungu t/a Welcome Car Hire And Transport

Plaintiff

National Water Conservation & Pipeline Corporation

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Was the Plaintiff contracted by the Defendant to provide services as pleaded?
  2. 2 What services were provided by the Plaintiff to the Defendant as admitted in the Defence?
  3. 3 Does the Defendant owe the Plaintiff any money, and if so, how much?

Ratio Decidendi

The court found that the Plaintiff had established, on a balance of probabilities, the existence of a contractual relationship with the Defendant, as evidenced by the LPOs and the Defendant's own admissions. The Plaintiff's evidence of services rendered and the amount claimed was unchallenged, as the Defendant neither produced evidence of payment nor contested the claim at trial. The court held that the Plaintiff had discharged the burden of proof required in civil proceedings and was entitled to judgment for the sum of Kshs.126,580,590.00, interest at court rates from the date of filing suit, and costs. The Defendant's failure to participate in the proceedings did not relieve the...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the Plaintiff against the Defendant for Kshs.126,580,590.00.