[2004] KEHC 92 (KLR)

[2004] KEHC 92 (KLR)

The court found that the plaintiff was entitled to payment for measured and certified works and retention moneys, totaling Ksh. 4,079,670, as these sums were properly due under the contract and supported by the evidence. The court held that the plaintiff was responsible for the delay in completion due to inadequate...

Source-derived case information.

Citation
[2004] KEHC 92 (KLR)
Parties
Plaintiff: Neliwa Builders and Civil Engineers Ltd; Defendant: Jacob Mgaru Solomon; Defendant: Astrid Solomon; Defendant: George Eric Solomon; Defendant: Bernard Glen Solomon
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 1093 of 1999
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff in part
Judges
MJA Emukule
Legal Topics
Building Contracts, Delay and Extension of Time, Quantum Meruit, Interest Awards, Retention Moneys, Damages for Breach
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Delay and Extension of Time Quantum Meruit Interest Awards Retention Moneys Damages for Breach

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 3 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Neliwa Builders and Civil Engineers Ltd

Plaintiff

Jacob Mgaru Solomon

Defendant

Astrid Solomon

Defendant

George Eric Solomon

Defendant

Bernard Glen Solomon

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Was the plaintiff entitled to the claimed sum for works done and prolongation costs under the building contract?
  2. 2 What was the cause of delay in completion of the project and who was responsible?
  3. 3 Were the additional valuations by the Quantity Surveyor valid and payable?

Ratio Decidendi

The court found that the plaintiff was entitled to payment for measured and certified works and retention moneys, totaling Ksh. 4,079,670, as these sums were properly due under the contract and supported by the evidence. The court held that the plaintiff was responsible for the delay in completion due to inadequate financing, insufficient labour, and poor planning, and that the reasons advanced for the delay (such as bad weather and material shortages) were either foreseeable or not substantiated. The court rejected the plaintiff's claim for prolongation costs and higher interest, finding no contractual basis for such claims. The defendants' claim for set-off or damages failed for lack of...

Court Disposition

judgment for the plaintiff in part

Orders

  • Judgment entered for the plaintiff in the sum of Ksh. 4,079,670.
  • Interest awarded at court rates from the date of filing suit until payment in full.