[2005] KEHC 1889 (KLR)

[2005] KEHC 1889 (KLR)

The court found that the plaintiff failed to establish a prima facie case with a probability of success for the grant of an injunction. The contract between the parties had effectively come to an end by 10/9/2002, as evidenced by the cessation of material supply, the plaintiff's removal of machinery from the site,...

Source-derived case information.

Citation
[2005] KEHC 1889 (KLR)
Parties
Plaintiff: Newspace Creators Ltd.; Defendant: The Municipal Council of Meru
Court
High Court
Court Station
High Court at Meru
Jurisdiction
Kenya
Case Number
Civil Case 11 of 2005
Procedural Posture
Chamber Summons Application / Ruling on Interlocutory Injunction
Outcome
application dismissed
Legal Topics
Interlocutory Injunctions, Breach of Contract, Quantification of Damages, Arbitration Clauses
Source Language
en
Civil Procedure Commercial and Corporate Interlocutory Injunctions Breach of Contract Quantification of Damages Arbitration Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Newspace Creators Ltd.

Plaintiff

The Municipal Council of Meru

Defendant

Procedural Posture

Chamber Summons Application / Ruling on Interlocutory Injunction

  1. 1 Whether the plaintiff is entitled to an interlocutory injunction restraining the defendant from awarding the construction tender to another contractor pending determination of the suit.
  2. 2 Whether the contract between the plaintiff and defendant was still subsisting at the time of the application.
  3. 3 Whether the plaintiff has established a prima facie case with a probability of success to warrant the grant of an injunction.

Ratio Decidendi

The court found that the plaintiff failed to establish a prima facie case with a probability of success for the grant of an injunction. The contract between the parties had effectively come to an end by 10/9/2002, as evidenced by the cessation of material supply, the plaintiff's removal of machinery from the site, and correspondence between the parties. The plaintiff had already quantified its claim for work done, and any alleged injury could be compensated by damages. Furthermore, the contract contained an arbitration clause requiring disputes to be referred to arbitration, which the plaintiff had not complied with by coming to court. The court held that there was no irreparable harm...

Court Disposition

application dismissed

Orders

  • The plaintiff's application for injunction is dismissed with costs to the defendant.
  • The temporary injunction issued on 28/01/2005 is discharged.