[2005] KEHC 3380 (KLR)

[2005] KEHC 3380 (KLR)

The court found that the plaintiff had not established a prima facie case with a probability of success for the grant of an interlocutory injunction. The contract between the parties had effectively come to an end by January 2005, as evidenced by the plaintiff's removal of machinery from the site and the...

Source-derived case information.

Citation
[2005] KEHC 3380 (KLR)
Parties
Plaintiff: Newspace Creators Ltd.; Defendant: The Municipal Council of Meru
Court
High Court
Court Station
High Court at Meru
Jurisdiction
Kenya
Case Number
Civil Case 11 of 2005
Procedural Posture
Civil Application / Ruling on Interlocutory Injunction Application
Outcome
application dismissed
Legal Topics
Interlocutory Injunctions, Breach of Contract, Quantification of Damages, Arbitration Clauses
Source Language
en
Commercial and Corporate Civil Procedure Interlocutory Injunctions Breach of Contract Quantification of Damages Arbitration Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Newspace Creators Ltd.

Plaintiff

The Municipal Council of Meru

Defendant

Procedural Posture

Civil Application / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiff is entitled to an interlocutory injunction restraining the defendant from awarding the tender for the Town Hall extension to another contractor pending determination of the suit.
  2. 2 Whether the contract between the plaintiff and defendant was still subsisting at the time of the application.
  3. 3 Whether the plaintiff has established a prima facie case with a probability of success to warrant the grant of an injunction.

Ratio Decidendi

The court found that the plaintiff had not established a prima facie case with a probability of success for the grant of an interlocutory injunction. The contract between the parties had effectively come to an end by January 2005, as evidenced by the plaintiff's removal of machinery from the site and the correspondence exchanged. The plaintiff had already quantified its claim for work done, and any loss suffered could be compensated by damages. There was no evidence that the plaintiff would suffer irreparable harm if the tender was awarded to another contractor. Furthermore, the contract contained an arbitration clause requiring disputes to be referred to arbitration, which the plaintiff...

Court Disposition

application dismissed

Orders

  • The plaintiff's application for an interlocutory injunction is dismissed with costs to the defendant.
  • The temporary injunction issued on 28/01/2005 is discharged.