https://new.kenyalaw.org/akn/ke/judgment/kecopt/2026/299

https://new.kenyalaw.org/akn/ke/judgment/kecopt/2026/299

The Tribunal held that the preliminary objection raised a pure point of law because it turned on jurisdiction and the mandatory wording of By-Law 79, but it lacked merit because the Respondent did not demonstrate that the internal dispute resolution process had in fact been opened to the Claimant. The Tribunal found...

Source-derived case information.

Citation
[2026] KECOPT 299 (KLR)
Parties
Claimant: ASBJORN FORLAND NGANI; Respondent: KUSCCO HOUSING COOPERATIVE SOCIETY LIMITED
Court
Cooperative Tribunal
Jurisdiction
Kenya
Case Number
Tribunal Case E985 of 2025
Procedural Posture
Co Operative Tribunal Preliminary Objection Ruling / Ruling on Notice of Preliminary Objection
Outcome
Preliminary objection dismissed with costs
Judges
["J Mwatsama", "B Sawe", "F Lotuiya", "M Chesikaw", "PO Aol"]
Legal Topics
Jurisdiction, Preliminary Objection, Exhaustion Doctrine, By Laws and Internal Dispute Resolution, Arbitration Clause, Sacco Dispute
Source Language
en
Co Operative Law Civil Procedure Alternative Dispute Resolution Jurisdiction Preliminary Objection Exhaustion Doctrine By Laws and Internal Dispute Resolution Arbitration Clause +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 14 Party arguments 1 Amounts and remedies 5
Sign in to unlock

Parties

ASBJORN FORLAND NGANI

Claimant

KUSCCO HOUSING COOPERATIVE SOCIETY LIMITED

Respondent

Procedural Posture

Co Operative Tribunal Preliminary Objection Ruling / Ruling on Notice of Preliminary Objection

  1. 1 Whether the Notice of Preliminary Objection met the threshold of a preliminary objection
  2. 2 Whether the Tribunal had jurisdiction in light of By-Law 79 and the alleged failure to exhaust internal dispute resolution mechanisms
  3. 3 Whether the Claimant was required to first pursue internal remedies before approaching the Tribunal

Ratio Decidendi

The Tribunal held that the preliminary objection raised a pure point of law because it turned on jurisdiction and the mandatory wording of By-Law 79, but it lacked merit because the Respondent did not demonstrate that the internal dispute resolution process had in fact been opened to the Claimant. The Tribunal found that, on the facts before it, the Claimant was before the Tribunal because the internal process was not made available to him, so dismissal of the claim at the threshold was unjustified.

Court Disposition

Preliminary objection dismissed with costs

Orders

  • Notice of Preliminary Objection dated 9th December 2025 dismissed with costs
  • Mention for pre-trial directions on 15/10/2026 before the ADR