[2023] KEELC 21858 (KLR)

[2023] KEELC 21858 (KLR)

The court found that while the petitioner was entitled to just compensation for the portion of land compulsorily acquired, the respondent was justified in revising the award due to changes in the road design and intervention by the EACC over concerns of fraud and overvaluation. The court held that compensation must...

Source-derived case information.

Citation
[2023] KEELC 21858 (KLR)
Parties
Applicant: Nguku Product Twenty Ten Limited; Respondent: National Land Commission
Court
Environment and Land Court
Court Station
Environment and Land Court at Machakos
Jurisdiction
Kenya
Case Number
Environment & Land Petition 25 of 2020
Procedural Posture
Constitutional Petition / Judgment
Outcome
petition struck out
Judges
CA Ochieng
Legal Topics
Compulsory Acquisition, Just Compensation, Valuation of Land, Jurisdiction of Land Acquisition Tribunal, Constitutional Rights to Property, Public Interest in Land Acquisition
Source Language
en
Land and Property Administrative Law Compulsory Acquisition Just Compensation Valuation of Land Jurisdiction of Land Acquisition Tribunal Constitutional Rights to Property Public Interest in Land Acquisition

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 13 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Nguku Product Twenty Ten Limited

Applicant

National Land Commission

Respondent

Procedural Posture

Constitutional Petition / Judgment

  1. 1 Whether the petitioner is entitled to payment of Kshs. 77,478,659 plus interest as just compensation for compulsorily acquired land.
  2. 2 Whether the respondent violated the petitioner's constitutional rights in revising the compensation award and withholding payment.
  3. 3 Whether the petition was properly before the court or should have been referred to the Land Acquisition Tribunal.

Ratio Decidendi

The court found that while the petitioner was entitled to just compensation for the portion of land compulsorily acquired, the respondent was justified in revising the award due to changes in the road design and intervention by the EACC over concerns of fraud and overvaluation. The court held that compensation must reflect the actual land acquired and that the petitioner failed to provide a current valuation report to challenge the revised award. Furthermore, the court determined that disputes arising from compulsory acquisition should first be referred to the Land Acquisition Tribunal, which is now operational and has the statutory mandate to resolve such matters. As the petitioner had...

Court Disposition

petition struck out

Orders

  • The petition is struck out as unmerited.