[2021] KEELC 3965 (KLR)

[2021] KEELC 3965 (KLR)

The court found that while the Respondents had taken possession of the Petitioner's land for the LAPSSET project, the formal process of compulsory acquisition as required by the Constitution and the Land Act was not fully followed, particularly regarding prompt compensation. The delay in compensation was partly...

Source-derived case information.

Citation
[2021] KEELC 3965 (KLR)
Parties
Applicant: Nightshade Properties Ltd; Respondent: The National Land Commission; Respondent: LAPSSET Corridor Development Authority; Respondent: The Honourable Attorney General; Respondent: Kenya Ports Authority
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Petition 33 of 2019
Procedural Posture
Constitutional Petition / Judgment
Outcome
petition_partially_allowed
Judges
JO Olola
Legal Topics
Compulsory Acquisition, Just Compensation, Public Purpose Land Use, Due Process in Land Acquisition, Statutory Interpretation, Government Agency Mandate
Source Language
en
Land and Property Constitutional Law Administrative Law Compulsory Acquisition Just Compensation Public Purpose Land Use Due Process in Land Acquisition Statutory Interpretation +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Nightshade Properties Ltd

Applicant

The National Land Commission

Respondent

LAPSSET Corridor Development Authority

Respondent

The Honourable Attorney General

Respondent

Kenya Ports Authority

Respondent

Procedural Posture

Constitutional Petition / Judgment

  1. 1 Whether the compulsory acquisition of the Petitioner's land was conducted in accordance with the Constitution and the Land Act.
  2. 2 Whether the Petitioner is entitled to just compensation for the compulsory acquisition of its property.
  3. 3 Whether Section 120 of the Land Act and certain provisions of the Kenya Ports Authority Act are unconstitutional for permitting possession before compensation.

Ratio Decidendi

The court found that while the Respondents had taken possession of the Petitioner's land for the LAPSSET project, the formal process of compulsory acquisition as required by the Constitution and the Land Act was not fully followed, particularly regarding prompt compensation. The delay in compensation was partly attributable to earlier disputes over the Petitioner's title, but once the title was validated, the National Land Commission was obligated to proceed with compensation. The court held that Section 120 of the Land Act, which allows possession before compensation in cases of urgency, is not unconstitutional as long as just compensation is ultimately paid. The actions of the...

Court Disposition

petition_partially_allowed

Orders

  • An order of mandamus is issued directing the 1st Respondent to convene a meeting under Section 112 of the Land Act to determine just compensation due to the Petitioner within 45 days.
  • In default, an injunction shall issue after 45 days restraining the 1st, 2nd, and 5th Respondents from remaining on or interfering with LR No. 28101 Mokowe Lamu.