[2022] KEHC 14621 (KLR)

[2022] KEHC 14621 (KLR)

The court found that while a contractual relationship existed and the plaintiff undertook additional works, the plaintiff failed to strictly prove its entitlement to the claimed sum of Kshs. 44,311,576.04. The plaintiff admitted having been paid amounts exceeding the original contract sum and did not produce...

Source-derived case information.

Citation
[2022] KEHC 14621 (KLR)
Parties
Plaintiff: Njama Company Limited; Defendant: University of Nairobi
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 175 of 2019
Procedural Posture
Civil Case / Judgment
Outcome
suit dismissed
Judges
WA Okwany
Legal Topics
Breach of Contract, Public Procurement, Special Damages, Arbitration Awards
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Public Procurement Special Damages Arbitration Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Njama Company Limited

Plaintiff

University of Nairobi

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether a contractual relationship existed between the Plaintiff and Defendant.
  2. 2 Whether the Defendant commissioned the Plaintiff to undertake the additional works.
  3. 3 Whether the Defendant is in breach of the contract.

Ratio Decidendi

The court found that while a contractual relationship existed and the plaintiff undertook additional works, the plaintiff failed to strictly prove its entitlement to the claimed sum of Kshs. 44,311,576.04. The plaintiff admitted having been paid amounts exceeding the original contract sum and did not produce essential documents such as the variation agreement, schedule of accounts, or the arbitral award. The court held that the final certificate alone was insufficient proof of debt, especially as the defendant refuted the claim and provided evidence of payments and correspondence limiting liability to a retention sum. The plaintiff's failure to comply with the Public Procurement and Asset...

Court Disposition

suit dismissed

Orders

  • The plaintiff's suit is dismissed.
  • Each party shall bear its own costs.