[2022] KEHC 15994 (KLR)

[2022] KEHC 15994 (KLR)

The court found that there was a valid arbitration agreement between the plaintiff and defendant, and that a dispute had arisen regarding the performance and advance payment guarantees. Although the interested party argued that the guarantees were independent contracts, the court held that in this context, the...

Source-derived case information.

Citation
[2022] KEHC 15994 (KLR)
Parties
Plaintiff: Njuca Consolidated Company; Defendant: Athi Water Works Development Agency; Interested Party: Equity Bank Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Suit E859 of 2021
Procedural Posture
Commercial Suit / Ruling on Interlocutory Applications and Preliminary Objection
Outcome
Plaintiff's applications for interim protection granted; preliminary objection dismissed.
Judges
A Mabeya
Legal Topics
Performance Guarantees, Advance Payment Guarantees, Arbitration Agreements, Interim Injunctions, Contractual Breach, Construction Contracts
Source Language
en
Commercial and Corporate Civil Procedure Performance Guarantees Advance Payment Guarantees Arbitration Agreements Interim Injunctions Contractual Breach Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Njuca Consolidated Company

Plaintiff

Athi Water Works Development Agency

Defendant

Equity Bank Limited

Interested Party

Procedural Posture

Commercial Suit / Ruling on Interlocutory Applications and Preliminary Objection

  1. 1 Whether the High Court has jurisdiction to grant interim measures of protection pending arbitration under section 7 of the Arbitration Act.
  2. 2 Whether the performance guarantee and advance payment guarantee are independent contracts or are connected to the underlying construction contract.
  3. 3 Whether the plaintiff is entitled to interim injunctive relief restraining the defendant and interested party from calling or paying the guarantees pending arbitration.

Ratio Decidendi

The court found that there was a valid arbitration agreement between the plaintiff and defendant, and that a dispute had arisen regarding the performance and advance payment guarantees. Although the interested party argued that the guarantees were independent contracts, the court held that in this context, the guarantees were intricately connected to the underlying construction contract and their enforcement depended on the resolution of the contractual dispute. The court further held that it had jurisdiction under section 7 of the Arbitration Act to grant interim measures of protection to preserve the subject matter of the arbitration. The defendant's preliminary objection was dismissed...

Court Disposition

Plaintiff's applications for interim protection granted; preliminary objection dismissed.

Orders

  • Prayers (a) and (b) of the application dated October 13, 2021 are granted pending determination of the arbitration.
  • The Chairman of the Architectural Society of Kenya is appointed as the sole appointing authority to appoint an arbitrator within 21 days of the date of this ruling.