https://new.kenyalaw.org/akn/ke/judgment/kehc/2026/7888
The claim was not time-barred because the dispute crystallized on 24 September 2020 when the demand for payment was ignored, the notice of dispute dated 7 December 2020 was within the contractual ninety-day period, and arbitration was commenced within the six-year statutory limitation period. The tribunal therefore...
Source-derived case information.
- Citation
- [2026] KEHC 7888 (KLR)
- Parties
- Plaintiff/applicant: Norkan Investments Ltd; Defendant/respondent: China Zhongxing Construction Company Ltd
- Court
- High Court
- Jurisdiction
- Kenya
- Case Number
- Civil Suit E733 of 2024
- Procedural Posture
- Commercial Civil Suit; Originating Summons Challenging Arbitral Preliminary Ruling on Jurisdiction and Limitation / Ruling on Originating Summons to Set Aside Preliminary Award/ruling
- Outcome
- Originating Summons dismissed for lack of merit.
- Judges
- ["BK Njoroge"]
- Legal Topics
- Jurisdiction of Arbitral Tribunal, Setting Aside Preliminary Award/ruling, Contractual Notice of Dispute, Accrual of Dispute in Construction Contract, Time Bar Under Limitation of Actions Act, Commencement of Arbitration, Costs
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Norkan Investments Ltd
Plaintiff/applicant
China Zhongxing Construction Company Ltd
Defendant/respondent
Procedural Posture
Commercial Civil Suit; Originating Summons Challenging Arbitral Preliminary Ruling on Jurisdiction and Limitation / Ruling on Originating Summons to Set Aside Preliminary Award/ruling
Legal Issues
- 1 Whether the arbitral tribunal’s ruling finding the claim not time-barred should be set aside.
- 2 Whether the dispute was notified within the contractual ninety-day period under Clause 45.3.
- 3 Whether the claim was commenced within the six-year limitation period under the Limitation of Actions Act.
Ratio Decidendi
The claim was not time-barred because the dispute crystallized on 24 September 2020 when the demand for payment was ignored, the notice of dispute dated 7 December 2020 was within the contractual ninety-day period, and arbitration was commenced within the six-year statutory limitation period. The tribunal therefore did not err in declining to strike out the claim, so there was no basis to set aside its preliminary ruling.
Court Disposition
Originating Summons dismissed for lack of merit.
Orders
- The Originating Summons dated 4 December 2024 is dismissed.
- Costs of the application are awarded to the Respondent.
Full Case Text
Judgment text and source record
1 paragraphs
Norkan Investments Ltd v China Zhongxing Construction Company Ltd (Civil Suit E733 of 2024) [2026] KEHC 7888 (KLR) (Commercial and Tax) (8 June 2026) (Ruling) Neutral citation: [2026] KEHC 7888 (KLR) Republic of Kenya In the High Court at Nairobi (Milimani Commercial Courts) Commercial and Tax Civil Suit E733 of 2024 BK Njoroge, J June 8, 2026 Between Norkan Investments Ltd Plaintiff and China Zhongxing Construction Company Ltd Defendant Ruling 1.This Ruling is in respect of an Originating Summons dated 4th December, 2024. It seeks to set aside a Ruling issued by the Learned Arbitrator during the course of the proceedings. This is when the Arbitrator declined to rule that the Arbitral proceedings were time barred bith by statute and the contract. Background Facts 2.The Plaintiff filed the Originating Summons dated 4th December 2024 seeking the following orders;a.That the Honourable Court be pleased to set aside the Ruling/Preliminary Award delivered by Isabella Njeri Wachira-Towey PhD FCIArb. on 4th November 2024 and uphold the Plaintiff's Preliminary Objection dated 28th June 2024.b.That this Honourable Court be pleased to issue such further Orders as it may deem fit, appropriate, and expedient to grant in the circumstances of this matter.c.That the cost of this Application and the Arbitration be borne by the Defendant. 3.The Application was supported by the Affidavit of Trevor Kanja. He stated that on or about 28th June, 2024, the Plaintiff filed a Notice of Preliminary Objection. He sought to have the Defendant’s claim in the arbitration struck out with costs. The objection was grounded on, inter alia, the assertion that the claims were time-barred under the Limitation of Actions Act and the governing construction contract. 4.The Plaintiff contended that the arbitral proceedings had been instituted well outside the statutory limitation period. That they were therefore fatally defective, prejudicial, and in violation of mandatory legal provisions. It maintained that the claims constituted a clear disregard of both statutory law and contractual timelines. Thus, it warranted dismissal at a preliminary stage. 5.However, the Arbitral Tribunal, in a Ruling/Preliminary Award delivered on 4th November, 2024, dismissed the Preliminary Objection. This prompted the Plaintiff—being dissatisfied with the decision—to move the Court seeking to set aside the said ruling. This is on grounds of errors in law and misapplication of the principles governing limitation and jurisdiction. 6.In response, the Defendant filed the Replying Affidavit of XU JIANSHENG sworn on 23rd January, 2025. The Defendant confirmed that it issued a notice of dispute dated 7th December, 2020 and invited the Plaintiff to concur in the appointment of an arbitrator. That upon the Plaintiff’s failure to do so, it subsequently filed an application dated 16th October, 2023 for such appointment. Although the notice of dispute and the application were not formally placed before the Tribunal, both parties had custody of and had exchanged the documents. That no objection was raised as to their absence. Consequently, the Tribunal treated arguments founded on them as uncontested. 7.The Defendant maintained that its right to institute arbitral proceedings remained valid under both the Limitation of Actions Act and Clause 45 of the Contract. No dispute arose at the time of delayed or non-payment in 2016, as the contractual remedy of interest on delayed payments was still operative. Rather, the dispute crystallized upon issuance of a demand letter dated 10th September, 2020. It required payment within 14 days and upon the Plaintiff’s failure to comply, by 24th September, 2020. 8.Accordingly, the Defendant asserted that the dispute arose on 24th September, 2020, and was duly notified by the letter of 7th December, 2020, within 74 days. By inviting concurrence on the appointment of an arbitrator in the same letter, the Defendant effectively commenced arbitral proceedings within the meaning of Section 22 of the Arbitration Act. Thus, its claim was neither time-barred under statute nor under Clause 45.3 of the Contract, having been brought within the prescribed timelines. Issues for determination 9.Having carefully considered the Application, response and the written submissions, the Court finds that there is only one issue for determination;a.Whether the Ruling/Preliminary Award delivered by Isabella Njeri Wachira-Towey PhD FCIArb. on 4th November 2024 should be set aside. Analysis 10.The Plaintiff’s Preliminary Objection before the Tribunal primarily pertained to the Arbitral Tribunal’s lack of jurisdiction. This is to entertain and adjudicate the claim filed by the Defendant as against the Plaintiff. This is on the ground that the subject claims are time and statute-barred. This is by operation of the provisions of the Agreement and Conditions of Contract for Building Works dated 10th June, 2015 between the parties herein as well as applicable laws. 11.It is trite law that under Section 17(6) of the Arbitration Act the Court has the jurisdiction to entertain an appeal on the Arbitrator’s ruling. The section provides that:“ 6.Where the arbitral tribunal rules as a preliminary question that it has jurisdiction, any party aggrieved by such ruling may apply to the High Court, within 30 days after having received notice of that ruling, to decide the matter.” 12.The Plaintiff argued that it is trite law that a party is bound by the terms of the contract to which it is a party. Accordingly, this Arbitral Tribunal ought to give effect to the plain and ordinary meaning of the subject agreement between the parties. The provisions of the Contract are clear and unambiguous. In the event the Defendant wished to refer any dispute or difference arising between itself and the Plaintiff, it was obligated to issue a notice of dispute. This in accordance with the Contract was within ninety (90) days of the occurrence or discovery of each matter or issue giving rise to the disputes forming the basis of its claims herein. 13.On the other hand, it was the Defendant’s contention that that arbitration commenced on 7th December, 2020. This is when it invited the Plaintiff to concur in the appointment of an arbitrator, within the meaning of the aforesaid provisions. Accordingly, any claim arising within six years preceding 7th December, 2020, namely between 7th December, 2014 and 7th December, 2020, fell within the statutory limitation period and is therefore enforceable. The Defendant’s claims are thus demonstrably within the prescribed six-year limitation period, as shall be further illustrated in the analysis of the second issue for determination. 14.Clause 45 of the Contract referred to by the parties’ states;“ 45.1 In case any dispute or difference shall arise between the Employer or the Architect on his behalf and the Contractor, either during the progress or after the completion or abandonment of the Works, such dispute shall be notified in writing by either party to the other with a request to submit it to arbitration and to concur in the appointment of an Arbitrator within thirty days of the notice. The dispute shall be referred to the arbitration and final decision of a person to be agreed between the parties. Failing agreement to concur in the appointment of an Arbitrator, the Arbitrator shall be appointed by the Chairman or Vice Chairman of The Architectural Association of Kenya, on the request of the applying party. 45.2 The arbitration may be on the construction of this contract or on any matter or thing of whatsoever nature arising thereunder or in connection therewith, including any matter or thing left by this contract to the discretion of the Architect, or the withholding by the Architect of any certificate to which the Contractor may claim to be entitled or the measurement and valuation referred to in clause 34.0 of these conditions, or the rights and liabilities of the parties subsequent to the termination of contract. 45.3 Provided that no arbitration proceedings shall be commenced on any dispute or difference where notice of a dispute or difference has not been given by the applying party within ninety days of the occurrence or discovery of the matter or issue giving rise to the dispute.” 15.In West Mount Investments Ltd Vs Tridev Builders Company Ltd [2017] eKLR, the Court held: -“a dispute arises when a claim is made by one party following the actions of another party and such claim is either rejected or ignored by the other party.” 16.It is the Court’s understanding that the final payment due under the Contract is embodied in the Final Certificate, which was issued by the Architect on 18th October, 2022. Pursuant to clause 34.21.3 of the Contract, if the amount certified was not paid within fourteen (14) days of presentation of the Final Certificate to the Employer, the same crystallized into a debt due and payable to the Defendant. Further, under clause 34.6 of the Contract, such debt attracted interest upon non-payment. Therefore, mere non-payment or delay in payment does not, of itself, constitute a dispute. Rather, a dispute only arises where a demand for payment of the principal sum and accrued interest, where applicable, is ignored, refused, or otherwise not honoured. 17.In this case, the Applicant’s failure to settle the sums demanded within fourteen (14) days of the demand letter dated 10th September, 2020 constituted the occurrence of the matter giving rise to the dispute. Consequently, the dispute crystallized on 24th September, 2020, thereby triggering the ninety (90) day period for issuance of a notice of dispute under Clause 45.3. 18.The Court is hereby inclined to agree with the Arbitrator. This is to the effect that the Claimant’s Notice of Dispute dated 7th December, 2020 was issued within the prescribed ninety (90) day period. This is under Clause 45.3, as were the Claimant’s other claims. 19.Further, taking into consideration Section 34 of the Limitation of Actions Act the event that triggered the arbitral proceedings herein, arose on 24th September, 2020. It follows that the commencement of arbitration on 7th December, 2020, within the meaning of Section 34(3) of the Limitation of Actions Act, fell within the statutory six-year limitation period prescribed under the Act. Further, the Claimant’s claims arising within the six years preceding commencement of the arbitration, namely between 2016 and 2019, are enforceable. 20.Accordingly, the Court finds that the Claimant’s claims are not time-barred. The Originating Summons fails. 21.As to costs, the same lie at the discretion of this Court and follow the event. The Court is persuaded that the fair and just order is to award the successful Respondent the costs of the application. Determination 22.The Application by the Applicant by way of an Originating Summons dated 4th December, 2024 is hereby dismissed for lack of merits. 23.The costs thereof are awarded to the Respondent. 24.It is so ordered. DATED, SIGNED AND DELIVERED AT MILIMANI THIS 08TH DAY OF JUNE, 2026.NJOROGE BENJAMIN K.JUDGEIn the presence of:Mr. Wachira for the Plaintiff.Miss Khizi for the Defendant.Mr. John Paul - Court Assistant.