[2023] KEELRC 2361 (KLR)

[2023] KEELRC 2361 (KLR)

The court found that since the respondent had formally abandoned its counterclaim, there was no longer any live issue for determination regarding the counterclaim. In the interests of justice and finality, the court marked the counterclaim as settled and ordered the closure of the matter. On the issue of costs, the...

Source-derived case information.

Citation
[2023] KEELRC 2361 (KLR)
Parties
Claimant: Albert W Nyandat; Respondent: Barclays Bank Of Kenya
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nairobi
Jurisdiction
Kenya
Case Number
Cause 124 of 2018
Procedural Posture
Employment Cause / Ruling on Counterclaim Settlement
Outcome
Counterclaim marked as settled; matter closed; each party to bear its own costs.
Judges
AN Mwaure
Legal Topics
Counterclaim Abandonment, Costs Award, Court Orders, Virtual Delivery of Rulings
Source Language
en
Employment and Labour Counterclaim Abandonment Costs Award Court Orders Virtual Delivery of Rulings

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Albert W Nyandat

Claimant

Barclays Bank Of Kenya

Respondent

Procedural Posture

Employment Cause / Ruling on Counterclaim Settlement

  1. 1 Whether the respondent's counterclaim should be marked as settled following its abandonment.
  2. 2 Who should bear the costs of the proceedings after the counterclaim is abandoned.

Ratio Decidendi

The court found that since the respondent had formally abandoned its counterclaim, there was no longer any live issue for determination regarding the counterclaim. In the interests of justice and finality, the court marked the counterclaim as settled and ordered the closure of the matter. On the issue of costs, the court exercised its discretion to direct that each party bear its own costs, considering the circumstances of the abandonment and the absence of a determination on the merits. The court also affirmed the propriety of delivering the ruling virtually, in accordance with constitutional and statutory provisions enabling the use of technology and eschewing undue technicalities,...

Court Disposition

Counterclaim marked as settled; matter closed; each party to bear its own costs.

Orders

  • The respondent's counterclaim is marked as settled.
  • The matter is closed.