[2018] KEELC 2223 (KLR)

[2018] KEELC 2223 (KLR)

The court found that the machinery sold to the plaintiff was obsolete and non-functional, and that the defendant, as a development financier with a mandate to supervise and support the project, failed in its duty to ensure the viability of the business. The defendant's delay of over 11 years before seeking to...

Source-derived case information.

Citation
[2018] KEELC 2223 (KLR)
Parties
Plaintiff: Nyange Business Links Limited; Defendant: Kenya Industrial Estates Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Meru
Jurisdiction
Kenya
Case Number
Environment & Land Case 132 of 2012
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's suit succeeds in part; contract declared frustrated; plaintiff owes no further monies; securities to be discharged; each party to bear own costs.
Legal Topics
Loan Default, Security Realization, Contract Frustration, Equipment Sale Dispute, Statutory Power of Sale
Source Language
en
Commercial and Corporate Land and Property Loan Default Security Realization Contract Frustration Equipment Sale Dispute Statutory Power of Sale

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Nyange Business Links Limited

Plaintiff

Kenya Industrial Estates Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 What were the terms of the agreement between plaintiff and defendant?
  2. 2 Whether the purchased equipment was overvalued.
  3. 3 Whether the machines were functional or not?

Ratio Decidendi

The court found that the machinery sold to the plaintiff was obsolete and non-functional, and that the defendant, as a development financier with a mandate to supervise and support the project, failed in its duty to ensure the viability of the business. The defendant's delay of over 11 years before seeking to realize the security was contrary to the terms of the agreement and rendered the statutory notice invalid. There was no certainty as to the outstanding amount by the time of default in 1999, and the defendant failed to provide a clear and contractual basis for the figures claimed. The contract was deemed frustrated due to the non-operational state of the machinery and the defendant's...

Court Disposition

Plaintiff's suit succeeds in part; contract declared frustrated; plaintiff owes no further monies; securities to be discharged; each party to bear own costs.

Orders

  • It is hereby declared that the agreement between the parties stands as frustrated.
  • It is hereby declared that plaintiff does not owe defendant any monies any more.