[2024] KEHC 923 (KLR)

[2024] KEHC 923 (KLR)

The court found that while there was a written lease agreement between the parties, it was not attested by a witness as required by Section 3(3) of the Law of Contract Act, rendering it unenforceable. Consequently, the plaintiff could not succeed in a claim for breach of contract or for damages arising therefrom,...

Source-derived case information.

Citation
[2024] KEHC 923 (KLR)
Parties
Plaintiff: Boniface Owiti Okiri; Defendant: Jiangxi Zhongmei Engineering Construction Co Ltd
Court
High Court
Court Station
High Court at Kisumu
Jurisdiction
Kenya
Case Number
Commercial Case 5 of 2019
Procedural Posture
Commercial Case / Judgment
Outcome
Specific performance ordered; all monetary claims dismissed; each party to bear own costs.
Judges
RE Aburili
Legal Topics
Breach of Contract, Lease Agreements, Specific Performance, Damages Quantification, Land Restoration, Contract Enforceability
Source Language
en
Commercial and Corporate Land and Property Breach of Contract Lease Agreements Specific Performance Damages Quantification Land Restoration Contract Enforceability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 21 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Boniface Owiti Okiri

Plaintiff

Jiangxi Zhongmei Engineering Construction Co Ltd

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether the lease agreement between the plaintiff and defendant was valid and enforceable under Section 3(3) of the Law of Contract Act.
  2. 2 Whether the defendant breached the terms of the lease agreement by failing to backfill and restore the plaintiff's land.
  3. 3 Whether the plaintiff is entitled to damages for loss of use of land, exemplary and aggravated damages, or the quantified cost of backfilling.

Ratio Decidendi

The court found that while there was a written lease agreement between the parties, it was not attested by a witness as required by Section 3(3) of the Law of Contract Act, rendering it unenforceable. Consequently, the plaintiff could not succeed in a claim for breach of contract or for damages arising therefrom, including general, exemplary, or aggravated damages. The court further held that even if the contract were enforceable, general damages are not awardable for breach of contract, and the plaintiff failed to specifically plead and prove special damages for loss of use of land. The expert evidence on loss of use was found unreliable and unsupported. The claim for the quantified cost...

Court Disposition

Specific performance ordered; all monetary claims dismissed; each party to bear own costs.

Orders

  • The defendant shall commence and complete the backfilling of the plaintiff's excavated land within ninety days in compliance with NEMA guidelines.
  • Each party shall bear its own costs of the suit.