[2024] KEELC 4748 (KLR)

[2024] KEELC 4748 (KLR)

The court found that the defendant was in breach of the sale agreement by failing to complete and deliver the apartment by the agreed date and failing to promptly notify the plaintiffs of any force majeure events as contractually required. The defendant's cited reasons for delay (material shortages and rainfall) did...

Source-derived case information.

Citation
[2024] KEELC 4748 (KLR)
Parties
Plaintiff: Esther Adhiambo Ongong; Plaintiff: Carilus Osambo Ademba; Defendant: Paragon Electronics Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 1205 of 2016
Procedural Posture
Environment and Land Case / Judgment
Outcome
Judgment for the plaintiffs; counter-claim partially allowed.
Judges
AA Omollo
Legal Topics
Sale of Land, Breach of Contract, Specific Performance, Force Majeure, Injunctions, Rental Income Disputes
Source Language
en
Land and Property Commercial and Corporate Sale of Land Breach of Contract Specific Performance Force Majeure Injunctions Rental Income Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Esther Adhiambo Ongong

Plaintiff

Carilus Osambo Ademba

Plaintiff

Paragon Electronics Limited

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the defendant was in breach of the sale agreement by failing to complete and deliver the apartment as agreed.
  2. 2 Whether the plaintiffs were entitled to specific performance or compensation for lost rental income.
  3. 3 Whether the defendant was entitled to payment of the outstanding lease premium balance.

Ratio Decidendi

The court found that the defendant was in breach of the sale agreement by failing to complete and deliver the apartment by the agreed date and failing to promptly notify the plaintiffs of any force majeure events as contractually required. The defendant's cited reasons for delay (material shortages and rainfall) did not qualify as force majeure under the agreement or law. The plaintiffs were not in default, as the final payment was contingent on completion and notice, which the defendant failed to provide. The plaintiffs were entitled to compensation for lost rental income as per the contract, calculated at Kshs. 100,000 per month from November 2013 to August 2020, less the outstanding...

Court Disposition

Judgment for the plaintiffs; counter-claim partially allowed.

Orders

  • A permanent injunction restraining the defendant from interfering with the plaintiffs' possession, rights, and use of Apartment 5 Block A-1 (now mislabeled as Apartment 6 in Block A-1).
  • Defendant to pay the plaintiffs lost rental income at Kshs. 100,000 per month from November 2013 to August 2020 (Kshs. 8,200,000) less the lease premium balance of Kshs. 1,630,000, amounting to Kshs. 6,570,000.