The court found that the defendant failed to meet the three cumulative conditions for grant of stay of execution pending appeal under Order 42 Rule 6 of the Civil Procedure Rules, 2010. Specifically, the defendant did not demonstrate substantial loss, as there was no evidence the plaintiff would be unable to refund...

Source-derived case information.

Citation
[2014] KEHC 8185 (KLR)
Parties
Plaintiff: Oriental Construction Company Limited; Defendant: Rift Valley Water Services Board
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 161 of 2012
Procedural Posture
Stay Application / Ruling on Application for Stay of Execution Pending Appeal
Outcome
Defendant's application for stay of execution pending appeal allowed; costs in the course.
Judges
CM Kamau
Legal Topics
Stay of Execution, Appeals Process, Security for Decretal Sum, Ex Parte Hearing, Service of Process
Source Language
en
Civil Procedure Commercial and Corporate Stay of Execution Appeals Process Security for Decretal Sum Ex Parte Hearing Service of Process

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Oriental Construction Company Limited

Plaintiff

Rift Valley Water Services Board

Defendant

Procedural Posture

Stay Application / Ruling on Application for Stay of Execution Pending Appeal

  1. 1 Whether the defendant satisfied the conditions for grant of stay of execution pending appeal under Order 42 Rule 6 of the Civil Procedure Rules, 2010.
  2. 2 Whether the defendant would suffer substantial loss if stay is not granted.
  3. 3 Whether the application for stay was made without unreasonable delay.

Ratio Decidendi

The court found that the defendant failed to meet the three cumulative conditions for grant of stay of execution pending appeal under Order 42 Rule 6 of the Civil Procedure Rules, 2010. Specifically, the defendant did not demonstrate substantial loss, as there was no evidence the plaintiff would be unable to refund the decretal sum if the appeal succeeded. The application for stay was made with unreasonable delay, as the defendant only acted after attachment of its goods, and no plausible explanation for the delay was provided. Although the defendant deposited the decretal sum as security, it did so outside the period directed by the court, and the temporary stay had lapsed. However, the...

Court Disposition

Defendant's application for stay of execution pending appeal allowed; costs in the course.

Orders

  • Stay of execution of the Ruling and Order of Mutava, J delivered on 12th July 2012 is granted pending the hearing and determination of Civil Appeal No 268 of 2012.