[2018] KEELC 4276 (KLR)

[2018] KEELC 4276 (KLR)

The court found that the plaintiffs and defendant entered into a valid off plan house purchase agreement for a maisonette at Elan Park Estate. The plaintiffs paid the deposit but the defendant failed to complete construction and transfer the unit, constituting a breach. The defendant's defence was struck out as a...

Source-derived case information.

Citation
[2018] KEELC 4276 (KLR)
Parties
Plaintiff: Oscar Ochieng; Plaintiff: Rachael Ayiko; Defendant: Prilcscot Company Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 464 of 2015
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiffs; specific performance granted; general damages denied; costs awarded to plaintiffs.
Judges
BM Eboso
Legal Topics
Specific Performance, Breach of Contract, Off Plan Purchase, Real Estate Development
Source Language
en
Land and Property Commercial and Corporate Specific Performance Breach of Contract Off Plan Purchase Real Estate Development

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Oscar Ochieng

Plaintiff

Rachael Ayiko

Plaintiff

Prilcscot Company Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant breached the off plan house purchase agreement by failing to complete construction and transfer the maisonette to the plaintiffs.
  2. 2 Whether the plaintiffs are entitled to an order of specific performance compelling the defendant to complete the sale and transfer the maisonette.
  3. 3 Whether the plaintiffs are entitled to general damages for breach of contract.

Ratio Decidendi

The court found that the plaintiffs and defendant entered into a valid off plan house purchase agreement for a maisonette at Elan Park Estate. The plaintiffs paid the deposit but the defendant failed to complete construction and transfer the unit, constituting a breach. The defendant's defence was struck out as a sham, leaving the plaintiffs' claim unchallenged. The court held that specific performance is appropriate as the defendant still holds title and there is no evidence of hardship or inability to convey. However, the plaintiffs are not entitled to general damages because they did not tender the balance of the purchase price at the time of filing suit. The court ordered specific...

Court Disposition

Judgment for the plaintiffs; specific performance granted; general damages denied; costs awarded to plaintiffs.

Orders

  • The defendant shall specifically perform the agreement for sale by completing the sale and transfer of Unit Number 161 Phase II, Elan Park Estate, to the plaintiffs.
  • The plaintiffs shall deposit the balance of the purchase price (Kshs 2,900,000) in court within 60 days; the court shall release the money to the defendant.