[2023] KEELC 17368 (KLR)

[2023] KEELC 17368 (KLR)

The court found that, since the 1st respondent denied any ongoing construction, granting the interim injunction sought in prayer 8 would not prejudice the respondent. The court applied the precautionary principle, noting that it was appropriate to forestall any further construction on the unregistered community land...

Source-derived case information.

Citation
[2023] KEELC 17368 (KLR)
Parties
Applicant: Abdirahiman Osman & 146 others; Respondent: Northern Rangeland Trust; Respondent: 2nd Respondent; Respondent: 8th and 9th Respondents
Court
Environment and Land Court
Court Station
Environment and Land Court at Isiolo
Jurisdiction
Kenya
Case Number
Environment & Land Petition 006 of 2021
Procedural Posture
Environment and Land Petition / Interlocutory Application for Interim Injunction
Outcome
Interim injunction granted as prayed in prayer 8 of the application, pending hearing of the application.
Judges
PM Njoroge
Legal Topics
Community Land Management, Interim Injunctions, Conservancy Operations, Precautionary Principle
Source Language
en
Land and Property Civil Procedure Community Land Management Interim Injunctions Conservancy Operations Precautionary Principle

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Abdirahiman Osman & 146 others

Applicant

Northern Rangeland Trust

Respondent

2nd Respondent

Respondent

8th and 9th Respondents

Respondent

Procedural Posture

Environment and Land Petition / Interlocutory Application for Interim Injunction

  1. 1 Whether the 1st respondent should be restrained by interim injunction from erecting structures on unregistered community land pending hearing of the application.
  2. 2 Whether the 1st respondent would suffer prejudice if the interim order is granted.
  3. 3 Whether the precautionary principle applies to the grant of interim orders in environmental and land matters.

Ratio Decidendi

The court found that, since the 1st respondent denied any ongoing construction, granting the interim injunction sought in prayer 8 would not prejudice the respondent. The court applied the precautionary principle, noting that it was appropriate to forestall any further construction on the unregistered community land pending the hearing of the application. The court was satisfied that the applicants had established a prima facie case for the grant of interim orders to preserve the status quo and prevent potential harm to the community land. Accordingly, the court granted prayer 8 of the application as an interim measure.

Court Disposition

Interim injunction granted as prayed in prayer 8 of the application, pending hearing of the application.

Orders

  • Prayer 8 in the application is granted pending hearing of this application.