[2014] KEHC 6095 (KLR)

[2014] KEHC 6095 (KLR)

The court found that both parties were aware of and accepted the delay in completion of construction, amounting to a mutual variation of the original contractual timeline. The Plaintiff did not enforce the original completion date nor demonstrate readiness to pay the balance of the purchase price when due. The...

Source-derived case information.

Citation
[2014] KEHC 6095 (KLR)
Parties
Plaintiff: Pamela Akinyi Wananda; Defendant: Bernard Kibe Ngunje
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Case 25 of 2009
Procedural Posture
Civil Case / Judgment
Outcome
plaintiff's suit dismissed with costs to the defendant
Judges
MM Kasango
Legal Topics
Sale of Land, Breach of Contract, Rescission of Contract, Specific Performance, Notice Requirements
Source Language
en
Land and Property Contract Law Sale of Land Breach of Contract Rescission of Contract Specific Performance Notice Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Pamela Akinyi Wananda

Plaintiff

Bernard Kibe Ngunje

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether there was a breach of the sale agreement for the suit property, and by whom.
  2. 2 Whether the Defendant was entitled to rescind the contract and refund the deposit.
  3. 3 Whether the Plaintiff was entitled to damages or specific performance for alleged breach.

Ratio Decidendi

The court found that both parties were aware of and accepted the delay in completion of construction, amounting to a mutual variation of the original contractual timeline. The Plaintiff did not enforce the original completion date nor demonstrate readiness to pay the balance of the purchase price when due. The Defendant, having completed construction and provided notice to complete to the Plaintiff's contractual address, was entitled to rescind the agreement upon the Plaintiff's failure to comply. The Plaintiff's claims of breach by the Defendant were unsupported, as the evidence showed mutual forbearance regarding time and proper notice of rescission. The Defendant's refund of the...

Court Disposition

plaintiff's suit dismissed with costs to the defendant

Orders

  • The Plaintiff's suit is dismissed.
  • The Plaintiff shall pay the costs of the suit to the Defendant.