The court found that a binding transportation agreement existed between the plaintiff and defendant, requiring delivery of goods by road within 12 days. The defendant's reliance on force majeure was rejected as the evidence did not support that torrential rains, power outages, or port congestion directly prevented...

Source-derived case information.

Citation
[2017] KEHC 7873 (KLR)
Parties
Plaintiff: Pankaj Transport Pvt Limited; Defendant: SDV Transami Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 162 of 2014
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff; defendant found liable for breach of contract.
Judges
DO Ogembo, GL Nzioka
Legal Topics
Breach of Contract, Force Majeure, Carriage of Goods, Damages Assessment, Privity of Contract
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Force Majeure Carriage of Goods Damages Assessment Privity of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Pankaj Transport Pvt Limited

Plaintiff

SDV Transami Kenya Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether there was a binding transportation agreement between the plaintiff and the defendant, and what its terms were.
  2. 2 Whether the transportation agreement was frustrated by force majeure or act of God events.
  3. 3 Whether the defendant is liable for consequential losses, including third-party claims and loss of business, arising from the alleged breach.

Ratio Decidendi

The court found that a binding transportation agreement existed between the plaintiff and defendant, requiring delivery of goods by road within 12 days. The defendant's reliance on force majeure was rejected as the evidence did not support that torrential rains, power outages, or port congestion directly prevented performance during the relevant periods. The defendant had contractual discretion to use alternative transport modes but failed to explain inconsistent use of road and rail or to deliver within a reasonable period. The court held the defendant liable for breach of contract, finding that the losses claimed for withheld payments and travel expenses were directly attributable to...

Court Disposition

Judgment for the plaintiff; defendant found liable for breach of contract.

Orders

  • The defendant shall pay the plaintiff USD 1,933,200 and INR 1,317,520 as compensation for losses suffered.