[2013] KEHC 3600 (KLR)

[2013] KEHC 3600 (KLR)

The court found that the third agreement dated 21st December, 2005 was voidable as it was executed under duress at the police station and thus unenforceable. The second agreement dated 8th March, 2005 was also unenforceable for lack of attestation as required by Section 3(3) of the Law of Contract Act. Only the...

Source-derived case information.

Citation
[2013] KEHC 3600 (KLR)
Parties
Plaintiff: Paola Da Fano; Defendant: Salim Abdalla Bakshwein
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 64 of 2006
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff in part; specific performance granted for portion A subject to payment of balance; counterclaim dismissed; each party to bear own costs.
Judges
CW Meoli
Legal Topics
Specific Performance, Breach of Contract, Unenforceable Agreements, Special Damages, Counterclaim, Title Transfer
Source Language
en
Land and Property Civil Procedure Specific Performance Breach of Contract Unenforceable Agreements Special Damages Counterclaim Title Transfer

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Paola Da Fano

Plaintiff

Salim Abdalla Bakshwein

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the agreements between the parties are valid and enforceable under Kenyan law.
  2. 2 Whether the plaintiff is entitled to specific performance and/or damages for breach of contract.
  3. 3 Whether the defendant is entitled to damages for false imprisonment and defamation as counterclaimed.

Ratio Decidendi

The court found that the third agreement dated 21st December, 2005 was voidable as it was executed under duress at the police station and thus unenforceable. The second agreement dated 8th March, 2005 was also unenforceable for lack of attestation as required by Section 3(3) of the Law of Contract Act. Only the first agreement dated 19th November, 2004, relating to portion A, was valid and enforceable. The plaintiff had paid half the purchase price, taken possession, and developed the land, while the defendant had prepared the deed plans but failed to complete the transfer. The plaintiff's claims for special damages (rerouting power lines, architectural fees, increased construction costs)...

Court Disposition

Judgment for the plaintiff in part; specific performance granted for portion A subject to payment of balance; counterclaim dismissed; each party to bear own costs.

Orders

  • Specific performance granted: defendant to complete subdivision and transfer of portion A (2610 sqm) to plaintiff upon plaintiff depositing KES 1,000,000 balance in court within 30 days.
  • If balance is not deposited within 30 days, the sum will attract interest at court rates.