[2016] KECA 522 (KLR)

[2016] KECA 522 (KLR)

The Court of Appeal found that while not all common area works were completed by the stipulated date, the parties subsequently varied the timelines by mutual agreement, and the appellant undertook to pay the balance and execute the sub-lease by new dates. The appellant failed to fulfill her obligations under this...

Source-derived case information.

Citation
[2016] KECA 522 (KLR)
Parties
Appellant: Patrizia Bini; Respondent: Melina Investment Limited; Respondent: Giuseppino Valsesia; Respondent: Paola Sasso; Respondent: Roberto Sasso
Court
Court of Appeal
Court Station
Court of Appeal at Malindi
Jurisdiction
Kenya
Case Number
Civil Appeal 54 of 2015
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
Appeal dismissed; damages award set aside; no order as to costs.
Judges
SP Ouko
Legal Topics
Sale of Land, Breach of Contract, Specific Performance, Damages for Trespass, Fraud Allegations, Title and Encumbrances
Source Language
en
Land and Property Commercial and Corporate Sale of Land Breach of Contract Specific Performance Damages for Trespass Fraud Allegations Title and Encumbrances

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Patrizia Bini

Appellant

Melina Investment Limited

Respondent

Giuseppino Valsesia

Respondent

Paola Sasso

Respondent

Roberto Sasso

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the respondents breached the preliminary sub-lease agreement by failing to complete common area works within the stipulated time.
  2. 2 Whether the appellant was justified in refusing to pay the balance of the purchase price and execute the sub-lease.
  3. 3 Whether the respondents committed fraud in offering the property for sale.

Ratio Decidendi

The Court of Appeal found that while not all common area works were completed by the stipulated date, the parties subsequently varied the timelines by mutual agreement, and the appellant undertook to pay the balance and execute the sub-lease by new dates. The appellant failed to fulfill her obligations under this revised arrangement, refused to execute the sub-lease, and did not pay the full balance. The alleged embargo and lack of approvals were not legal impediments to transfer, as the embargo was administrative and had been lifted, and building approvals existed. The appellant's continued possession after rescission of the agreement and failure to pay constituted trespass. However, the...

Court Disposition

Appeal dismissed; damages award set aside; no order as to costs.

Orders

  • The award of Kshs.7,000,000 as damages for trespass is set aside.
  • The appeal is dismissed.