[2020] KEHC 6206 (KLR)

[2020] KEHC 6206 (KLR)

The court found that although the original contract was awarded to a joint venture, subsequent conduct and documentation established that Sapamo Consultants was treated as a party for all practical purposes. The contract was validly performed and variations for splitting the project were approved by the tender...

Source-derived case information.

Citation
[2020] KEHC 6206 (KLR)
Parties
Plaintiff: Paul T Gichuhi t/a Sapamo Consulting Engineers; Defendant: Kenya Pipeline Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 928 of 2009
Procedural Posture
Civil Case / Judgment
Outcome
judgment for plaintiff in part; counterclaim dismissed; each party to bear own costs
Judges
GL Nzioka
Legal Topics
Public Procurement Contracts, Contract Variation, Locus Standi, Joint Ventures, Statute of Limitations, Interest on Judgments
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Contracts Contract Variation Locus Standi Joint Ventures Statute of Limitations Interest on Judgments

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 18 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Paul T Gichuhi t/a Sapamo Consulting Engineers

Plaintiff

Kenya Pipeline Company Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Does the plaintiff have locus standi to institute the suit.
  2. 2 Was there a valid contract between the parties and was it varied in accordance with the law.
  3. 3 Were the contract variations and extra works compliant with statutory procurement requirements.

Ratio Decidendi

The court found that although the original contract was awarded to a joint venture, subsequent conduct and documentation established that Sapamo Consultants was treated as a party for all practical purposes. The contract was validly performed and variations for splitting the project were approved by the tender committee and ratified by the board. However, extra works forming the basis of the plaintiff's claim were performed without a formal contract after the Public Procurement and Disposal Act, 2005 came into force, making statutory compliance mandatory. The court held that the parties' mutual understanding at the meeting of 12th February 2009, where a sum of Kshs. 21,094,637 was agreed...

Court Disposition

judgment for plaintiff in part; counterclaim dismissed; each party to bear own costs

Orders

  • Judgment entered for the plaintiff in the sum of Kshs. 10,547,318.50.
  • Interest at court rates from the date of judgment until payment in full.