[1982] KEHC 48 (KLR)

[1982] KEHC 48 (KLR)

The court found that the plaintiff's claims for damages due to delay and defects in construction were not sustainable. The delay was primarily caused by the plaintiff's failure to pay the contractor promptly, leading to work stoppages. The contract did not make time of the essence, and the plaintiff, by signing the...

Source-derived case information.

Citation
[1982] KEHC 48 (KLR)
Parties
Plaintiff: Peter Njoroge; Defendant: Ess Builders & Company
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 3497 of 1981
Procedural Posture
Civil Case / Judgment
Outcome
suit dismissed with costs
Judges
E Cotran
Legal Topics
Building Contracts, Breach of Contract, Damages for Delay, Waiver of Rights, Res Judicata, Construction Disputes
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Breach of Contract Damages for Delay Waiver of Rights Res Judicata Construction Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Peter Njoroge

Plaintiff

Ess Builders & Company

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff is entitled to damages for delay in completion of the building contract.
  2. 2 Whether the plaintiff waived his rights to claim for defects in construction by signing the December 8, 1979 letter.
  3. 3 Whether the defendant is liable for alleged missing materials from the construction site.

Ratio Decidendi

The court found that the plaintiff's claims for damages due to delay and defects in construction were not sustainable. The delay was primarily caused by the plaintiff's failure to pay the contractor promptly, leading to work stoppages. The contract did not make time of the essence, and the plaintiff, by signing the December 8, 1979 letter, expressly acknowledged satisfaction with the works and waived any further claims regarding defects or delay. The court also held that the issue of res judicata did not arise, as the previous suit was limited to the dishonoured cheque and did not address the substantive issues of the building contract or alleged losses. On the claim for missing...

Court Disposition

suit dismissed with costs

Orders

  • The plaintiff's suit is dismissed with costs to the defendant.