[2004] KEHC 2291 (KLR)

[2004] KEHC 2291 (KLR)

The court found that the applicant had fully complied with the first part of the consent order by paying the auctioneer and storage charges, entitling them to immediate release of the motor vehicles. The delay in depositing the decretal sum was not due to any fault of the applicant but was caused by the bank's...

Source-derived case information.

Citation
[2004] KEHC 2291 (KLR)
Parties
Appellant: Peterson Kamau; Appellant: Victor Majani; Respondent: Daniel Muli Mulwa; Respondent: Lonrho Motors E. A Ltd; Respondent: Stephen Dereva; Respondent: Bernard Gicheru; Defendant: The Attorney General
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
? 157 of 2004
Procedural Posture
Civil Appeal / Ruling on Application for Extension of Time and Related Orders
Outcome
application allowed
Legal Topics
Extension of Time, Consent Orders, Compliance With Court Orders, Auctioneer Charges
Source Language
en
Civil Procedure Extension of Time Consent Orders Compliance With Court Orders Auctioneer Charges

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Peterson Kamau

Appellant

Victor Majani

Appellant

Daniel Muli Mulwa

Respondent

Lonrho Motors E. A Ltd

Respondent

Stephen Dereva

Respondent

Bernard Gicheru

Respondent

The Attorney General

Defendant

Procedural Posture

Civil Appeal / Ruling on Application for Extension of Time and Related Orders

  1. 1 Whether the applicant is entitled to an extension of time to deposit the decretal sum as per the consent order.
  2. 2 Whether the applicant is entitled to the immediate release of motor vehicles upon payment of auctioneer and storage charges.
  3. 3 Whether Section 95 of the Civil Procedure Act applies to consent orders for purposes of extension of time.

Ratio Decidendi

The court found that the applicant had fully complied with the first part of the consent order by paying the auctioneer and storage charges, entitling them to immediate release of the motor vehicles. The delay in depositing the decretal sum was not due to any fault of the applicant but was caused by the bank's internal procedures and lack of cooperation from the respondent. The respondent's refusal to release the vehicles was unjustified and contrary to the spirit of the court order. The court held that Section 95 of the Civil Procedure Act applies to consent orders for the purpose of extending time, and the applicant was not seeking a variation of the order but merely an extension due to...

Court Disposition

application allowed

Orders

  • Time for depositing the decretal sum is extended by two weeks from the date of the ruling.
  • The applicant is entitled to immediate release of the motor vehicles upon payment of auctioneer and storage charges.