[2019] KEHC 11704 (KLR)

[2019] KEHC 11704 (KLR)

The court found that the Defendant's delay in prosecuting its Notice of Motion application was excusable due to the existence of a statutory moratorium declared under Section 67C(10) of the Insurance Act, which stayed all proceedings and execution against the insurer and its insureds. The court held that it could...

Source-derived case information.

Citation
[2019] KEHC 11704 (KLR)
Parties
Plaintiff: Phyllis Wangui Njau; Defendant: Heritage Contractors Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 2077 of 1999
Procedural Posture
Civil Suit / Ruling on Notice of Motion to Dismiss Defendant's Application and Allow Execution of Judgment
Outcome
Plaintiff's Notice of Motion application dated 27th March 2017 dismissed with costs to the Defendant.
Judges
CM Kamau
Legal Topics
Dismissal for Want of Prosecution, Execution of Judgment, Moratorium Under Insurance Act, Stay of Proceedings
Source Language
en
Civil Procedure Commercial and Corporate Dismissal for Want of Prosecution Execution of Judgment Moratorium Under Insurance Act Stay of Proceedings

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 12 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Phyllis Wangui Njau

Plaintiff

Heritage Contractors Ltd

Defendant

Procedural Posture

Civil Suit / Ruling on Notice of Motion to Dismiss Defendant's Application and Allow Execution of Judgment

  1. 1 Whether the Defendant's Notice of Motion application dated 22nd July 2013 should be dismissed for want of prosecution.
  2. 2 Whether the Plaintiff should be allowed to execute the judgment dated 14th December 2012 in light of the moratorium under the Insurance Act.
  3. 3 Whether the moratorium declared under Section 67C(10) of the Insurance Act bars execution and further proceedings against the Defendant.

Ratio Decidendi

The court found that the Defendant's delay in prosecuting its Notice of Motion application was excusable due to the existence of a statutory moratorium declared under Section 67C(10) of the Insurance Act, which stayed all proceedings and execution against the insurer and its insureds. The court held that it could not override the statutory powers of the statutory manager or contradict a court order from a court of equal jurisdiction. Furthermore, the Plaintiff's application to dismiss the Defendant's Notice of Motion was not merited, as Order 17 Rule 2(3) of the Civil Procedure Rules applies only to suits, not interlocutory applications. The Plaintiff could not execute the judgment while...

Court Disposition

Plaintiff's Notice of Motion application dated 27th March 2017 dismissed with costs to the Defendant.

Orders

  • The Plaintiff's Notice of Motion application dated 27th March 2017 is dismissed.