[2025] KEHC 4006 (KLR)

[2025] KEHC 4006 (KLR)

The court found that the parties had expressly agreed to resolve disputes through arbitration, and that the Plaintiff's application for interim protection was not premature given the Defendant's termination of the contracts and the Plaintiff's substantial performance. The court held that under Section 7 of the...

Source-derived case information.

Citation
[2025] KEHC 4006 (KLR)
Parties
Plaintiff: Power Parts (Kenya) Limited; Defendant: Kenya Ports Authority
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Commercial Case E070 of 2024
Procedural Posture
Commercial Case / Ruling on Interlocutory Application for Interim Protection and Reference to Arbitration
Outcome
Application allowed in part; matter referred to arbitration and interim injunction granted; each party to bear own costs.
Judges
F Wangari
Legal Topics
Arbitration Agreements, Interim Measures, Contract Termination, Public Procurement Disputes
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreements Interim Measures Contract Termination Public Procurement Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2
Sign in to unlock

Parties

Power Parts (Kenya) Limited

Plaintiff

Kenya Ports Authority

Defendant

Procedural Posture

Commercial Case / Ruling on Interlocutory Application for Interim Protection and Reference to Arbitration

  1. 1 Whether the Plaintiff is entitled to interim protection measures in the nature of an injunction pending arbitration.
  2. 2 Whether the dispute should be referred to arbitration as per the contract.
  3. 3 Whether the Plaintiff's application was premature in light of the contractual dispute resolution mechanism.

Ratio Decidendi

The court found that the parties had expressly agreed to resolve disputes through arbitration, and that the Plaintiff's application for interim protection was not premature given the Defendant's termination of the contracts and the Plaintiff's substantial performance. The court held that under Section 7 of the Arbitration Act, it had jurisdiction to grant interim measures to preserve the subject matter of the arbitration. The court determined that an injunction restraining the Defendant from upholding the termination of the contracts was appropriate to prevent the dissipation of the subject matter and to ensure the effectiveness of the arbitral process. The court also found that the issue...

Court Disposition

Application allowed in part; matter referred to arbitration and interim injunction granted; each party to bear own costs.

Orders

  • The application dated 5th December, 2024 is allowed in terms of prayers (d) and (e): the matter is referred to arbitration and an interim injunction is granted restraining the Defendant from upholding the termination of the contracts pending arbitration.
  • Parties are directed to comply with clause 10(2)(i) of the contracts regarding appointment of arbitrator within thirty (30) days, failing which the procedure in clause 10(2)(i)(a)-(d) shall apply.